项目管理期末复习WJH
搜索
项目管理期末复习WJH
题目内容
(
单选题
)
94. Which process involves gaining stakeholder and customer acceptance of the final products and
services and bringing the project, or project phase, to an orderly end?

A、 executing

B、 closing

C、 planning

D、 monitoring

答案:B

项目管理期末复习WJH
174. What needs are at the bottom of Maslow’s structure?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-b678-c0f9-29e3bb5dbe00.html
点击查看题目
166. Which is an output of schedule control?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-a6d8-c0f9-29e3bb5dbe00.html
点击查看题目
40. Which perspective on organizations assumes that organizations are coalitions composed of
varied individuals and interest groups?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-a8f0-c0f9-29e3bb5dbe01.html
点击查看题目
88. What is often the most difficult and unappreciated process in project management?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-0e80-c0f9-29e3bb5dbe00.html
点击查看题目
21. Which goal distinguishes project management and portfolio management?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-81e0-c0f9-29e3bb5dbe01.html
点击查看题目
186. According to Thamhain and Wilemon, what is the legitimate hierarchical right to issue orders?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-cde8-c0f9-29e3bb5dbe00.html
点击查看题目
200. In the Tuckman model, what occurs when the emphasis is on reaching the team goals, rather
than working on team process?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-e558-c0f9-29e3bb5dbe01.html
点击查看题目
39. The symbolic perspective of an organization:
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-a8f0-c0f9-29e3bb5dbe00.html
点击查看题目
43. In a organizational structure, program managers, rather than functional managers or vice
presidents, report to the CEO. Their staffs have a variety of skills needed to complete all required
tasks within their programs.
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-b0c0-c0f9-29e3bb5dbe01.html
点击查看题目
105. Which action involves reviewing the project charter, requirements documents, and
organizational process assets to create a scope statement, adding more information as requirements are developed and change requests are approved?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-2dc0-c0f9-29e3bb5dbe01.html
点击查看题目
首页
>
IT互联网
>
项目管理期末复习WJH
题目内容
(
单选题
)
手机预览
项目管理期末复习WJH

94. Which process involves gaining stakeholder and customer acceptance of the final products and
services and bringing the project, or project phase, to an orderly end?

A、 executing

B、 closing

C、 planning

D、 monitoring

答案:B

分享
项目管理期末复习WJH
相关题目
174. What needs are at the bottom of Maslow’s structure?

A.  esteem

B.  self-actualization

C.  physiological

D.  social

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-b678-c0f9-29e3bb5dbe00.html
点击查看答案
166. Which is an output of schedule control?

A.  change requests

B.  activity attributes

C.  resource requirements

D.  milestones lists

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-a6d8-c0f9-29e3bb5dbe00.html
点击查看答案
40. Which perspective on organizations assumes that organizations are coalitions composed of
varied individuals and interest groups?

A.  Political frame

B.  Symbolic frame

C.  Structural frame

D.  Human resources frame

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-a8f0-c0f9-29e3bb5dbe01.html
点击查看答案
88. What is often the most difficult and unappreciated process in project management?

A.  initiating

B.  planning

C.  Executing

D.  monitoring and controlling

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-0e80-c0f9-29e3bb5dbe00.html
点击查看答案
21. Which goal distinguishes project management and portfolio management?

A.  Project management involves making wise investment decisions whereas portfolio
management does not.

B.  Portfolio management is an easy task whereas project management is a more difficult task.

C.  Portfolio management asks questions like, “Are we carrying out projects efficiently?”
whereas project management asks questions such as “Are we investing in the right areas?”

D.  Project management addresses specific, short-term goals whereas portfolio management focuses on long-term goals.

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-81e0-c0f9-29e3bb5dbe01.html
点击查看答案
186. According to Thamhain and Wilemon, what is the legitimate hierarchical right to issue orders?

A.  authority

B.  achievement

C.  expertise

D.  self-actualization

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-cde8-c0f9-29e3bb5dbe00.html
点击查看答案
200. In the Tuckman model, what occurs when the emphasis is on reaching the team goals, rather
than working on team process?

A.  performing

B.  norming

C.  forming

D.  storming

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-e558-c0f9-29e3bb5dbe01.html
点击查看答案
39. The symbolic perspective of an organization:

A.  focuses on different groups’ roles and responsibilities to meet the goals and policies set
by top management.

B.  views the organization as coalitions composed of varied individuals and interest groups.

C.  focuses on providing harmony between the needs of the organization and the needs of
people.

D.  focuses on the meanings of the culture, language, traditions, and image of the organization.

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-a8f0-c0f9-29e3bb5dbe00.html
点击查看答案
43. In a organizational structure, program managers, rather than functional managers or vice
presidents, report to the CEO. Their staffs have a variety of skills needed to complete all required
tasks within their programs.

A.  project

B.  symbolic

C.  matrix

D.  functional

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-b0c0-c0f9-29e3bb5dbe01.html
点击查看答案
105. Which action involves reviewing the project charter, requirements documents, and
organizational process assets to create a scope statement, adding more information as requirements are developed and change requests are approved?

A.  Creating scope

B.  Defining scope

C.  Controlling scope

D.  Validating scope

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-2dc0-c0f9-29e3bb5dbe01.html
点击查看答案