90. What tool provides a basis for creating the project schedule and performing earned value
management for measuring and forecasting project performance?

A、 scope statement

B、 cost management plan

C、 work breakdown structure

D、 project charter

答案:C

项目管理期末复习WJH
62. Which systems development life cycle model assumes that requirements will remain stable after they are defined?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-dbb8-c0f9-29e3bb5dbe00.html
点击查看题目
178. According to Herzberg, which is a motivational factor?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-be48-c0f9-29e3bb5dbe00.html
点击查看题目
69. Which observation is true of the agile approach to software development?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-e770-c0f9-29e3bb5dbe01.html
点击查看题目
168. Which process involves building individual and group skills to enhance project performance?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-aac0-c0f9-29e3bb5dbe00.html
点击查看题目
19. Which statement is true of project management?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-7df8-c0f9-29e3bb5dbe01.html
点击查看题目
164. What is an accurate difference between the Program Evaluation and Review Technique ( ) and critical path method ( )?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-a2f0-c0f9-29e3bb5dbe00.html
点击查看题目
142. Which dependencies are sometimes referred to as soft logic and should be used with care
because they may limit later scheduling options?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-77f8-c0f9-29e3bb5dbe00.html
点击查看题目
174. What needs are at the bottom of Maslow’s structure?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-b678-c0f9-29e3bb5dbe00.html
点击查看题目
111. Which document contains a deliverable-oriented grouping of the work involved in a project
that defines the total scope of the project?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-3978-c0f9-29e3bb5dbe01.html
点击查看题目
79. What is developed in the Project Integration Management knowledge area?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-fee0-c0f9-29e3bb5dbe00.html
点击查看题目
首页
>
IT互联网
>
项目管理期末复习WJH
题目内容
(
单选题
)
手机预览
项目管理期末复习WJH

90. What tool provides a basis for creating the project schedule and performing earned value
management for measuring and forecasting project performance?

A、 scope statement

B、 cost management plan

C、 work breakdown structure

D、 project charter

答案:C

分享
项目管理期末复习WJH
相关题目
62. Which systems development life cycle model assumes that requirements will remain stable after they are defined?

A.  Spiral life cycle

B.  Waterfall life cycle

C.  Prototyping life cycle

D.  RAD life cycle

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-dbb8-c0f9-29e3bb5dbe00.html
点击查看答案
178. According to Herzberg, which is a motivational factor?

A.  recognition

B.  salary

C.  training

D.  health benefits

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-be48-c0f9-29e3bb5dbe00.html
点击查看答案
69. Which observation is true of the agile approach to software development?

A.  In the agile method, requirements and solutions evolve through collaboration.

B.  An agile approach sets scope goals, but leaves time and cost goals flexible.

C.  Agile is a predictive model of software development.

D.  In the agile approach, requirements must be clearly expressed early in the life cycle.

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-e770-c0f9-29e3bb5dbe01.html
点击查看答案
168. Which process involves building individual and group skills to enhance project performance?

A.  developing the human resource plan

B.  developing the project team

C.  acquiring the project team

D.  managing the project team

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-aac0-c0f9-29e3bb5dbe00.html
点击查看答案
19. Which statement is true of project management?

A.  It is a simple discipline with a limited scope.

B.  It has specific tools which work universally across all kinds of projects.

C.  It does not guarantee successes for all projects.

D.  Its framework consists solely of project management knowledge areas.

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-7df8-c0f9-29e3bb5dbe01.html
点击查看答案
164. What is an accurate difference between the Program Evaluation and Review Technique ( ) and critical path method ( )?

A.  CPM addresses the risk associated with duration estimates whereas PERT does not.

B.  Unlike CPM, PERT estimates only when there is no risk of uncertainty.

C.  CPM involves more work than PERT because it requires several duration estimates.

D.  PERT uses different duration estimates whereas CPM uses one specific duration estimate.

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-a2f0-c0f9-29e3bb5dbe00.html
点击查看答案
142. Which dependencies are sometimes referred to as soft logic and should be used with care
because they may limit later scheduling options?

A.  mandatory

B.  discretionary

C.  external

D.  inherent

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-77f8-c0f9-29e3bb5dbe00.html
点击查看答案
174. What needs are at the bottom of Maslow’s structure?

A.  esteem

B.  self-actualization

C.  physiological

D.  social

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-b678-c0f9-29e3bb5dbe00.html
点击查看答案
111. Which document contains a deliverable-oriented grouping of the work involved in a project
that defines the total scope of the project?

A.  project charter

B.  business case

C.  project scope statement

D.  work breakdown structure

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-3978-c0f9-29e3bb5dbe01.html
点击查看答案
79. What is developed in the Project Integration Management knowledge area?

A.  schedule management plan

B.  project management plan

C.  WBS

D.  quality management

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-fee0-c0f9-29e3bb5dbe00.html
点击查看答案
试题通小程序
试题通app下载