题目内容
(
单选题
)
71. What processes include devising and maintaining a workable scheme to ensure that the project
addresses the organization’s needs?

A、 Initiating

B、 Planning

C、 Executing

D、 Monitoring and controlling

答案:B

试题通
项目管理期末复习WJH
试题通
23. Which of the following questions reflects the strategic goals of project portfolio management?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-89b0-c0f9-29e3bb5dbe00.html
点击查看题目
85. What is one of the main outputs of the initiation process?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-0a98-c0f9-29e3bb5dbe00.html
点击查看题目
49. Which characteristic of organizational culture describes the degree to which management’s
decisions take into account the effect of outcomes on people within the organization?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-bc78-c0f9-29e3bb5dbe01.html
点击查看题目
20. Which of the following is true of program managers?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-81e0-c0f9-29e3bb5dbe00.html
点击查看题目
27. A Gantt chart is a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a format.
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-9180-c0f9-29e3bb5dbe00.html
点击查看题目
45. In what type of organizational structure do project managers have the most authority?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-b4a8-c0f9-29e3bb5dbe01.html
点击查看题目
63. In which systems development life cycle do model developers use a model to generate functional requirements and physical design specifications simultaneously?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-dbb8-c0f9-29e3bb5dbe01.html
点击查看题目
191. What term is used for taking time to renew oneself physically, spiritually, mentally and socially?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-d5b8-c0f9-29e3bb5dbe01.html
点击查看题目
124. Which term refers to the difference between planned and actual performance?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-54d0-c0f9-29e3bb5dbe00.html
点击查看题目
116. Which approach for constructing a WBS involves refining the work into greater and greater
levels of detail?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-4530-c0f9-29e3bb5dbe00.html
点击查看题目
首页
>
IT互联网
>
项目管理期末复习WJH
题目内容
(
单选题
)
手机预览
试题通
项目管理期末复习WJH

71. What processes include devising and maintaining a workable scheme to ensure that the project
addresses the organization’s needs?

A、 Initiating

B、 Planning

C、 Executing

D、 Monitoring and controlling

答案:B

试题通
分享
试题通
试题通
项目管理期末复习WJH
相关题目
23. Which of the following questions reflects the strategic goals of project portfolio management?

A.  Are we carrying out projects well?

B.  Are projects on time and on budget?

C.  Are we investing in the right areas?

D.  Do stakeholders know what they should be doing?

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-89b0-c0f9-29e3bb5dbe00.html
点击查看答案
85. What is one of the main outputs of the initiation process?

A.  creating the work breakdown structure

B.  selecting the project manager

C.  developing the project charter

D.  identifying the project sponsor

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-0a98-c0f9-29e3bb5dbe00.html
点击查看答案
49. Which characteristic of organizational culture describes the degree to which management’s
decisions take into account the effect of outcomes on people within the organization?

A.  Member identity

B.  Group emphasis

C.  People focus

D.  Unit integration

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-bc78-c0f9-29e3bb5dbe01.html
点击查看答案
20. Which of the following is true of program managers?

A.  They report to project managers who represent the next level in the hierarchy.

B.  They recognize that managing a program is simpler than managing a project.

C.  They provide leadership and direction for project managers heading the projects within a
program.

D.  They are responsible solely for the delivery of project results.

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-81e0-c0f9-29e3bb5dbe00.html
点击查看答案
27. A Gantt chart is a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a format.

A.  calendar

B.  line graph

C.  bar graph

D.  pie chart

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-9180-c0f9-29e3bb5dbe00.html
点击查看答案
45. In what type of organizational structure do project managers have the most authority?

A.  Functional

B.  Project

C.  Matrix

D.  Circular

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-b4a8-c0f9-29e3bb5dbe01.html
点击查看答案
63. In which systems development life cycle do model developers use a model to generate functional requirements and physical design specifications simultaneously?

A.  RAD life cycle

B.  Prototyping life cycle

C.  Spiral life cycle

D.  Waterfall life cycle

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-dbb8-c0f9-29e3bb5dbe01.html
点击查看答案
191. What term is used for taking time to renew oneself physically, spiritually, mentally and socially?

A.  empathic mirroring

B.  sharpening the saw

C.  synergizing

D.  thinking win/win

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-d5b8-c0f9-29e3bb5dbe01.html
点击查看答案
124. Which term refers to the difference between planned and actual performance?

A.  Decomposition

B.  Variance

C.  Scope validation

D.  Scope creep

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-54d0-c0f9-29e3bb5dbe00.html
点击查看答案
116. Which approach for constructing a WBS involves refining the work into greater and greater
levels of detail?

A.  analogy

B.  bottom-up

C.  top-down

D.  mind mapping

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-4530-c0f9-29e3bb5dbe00.html