70. What processes include defining and authorizing a project or project phase?

A、 Initiating

B、 Planning

C、 Executing

D、 Monitoring and controlling

答案:A

试题通
项目管理期末复习WJH
试题通
181. According to McClelland’s acquired-needs theory, what do people who want to direct others,
and can be seen as bossy, have a need for?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-c230-c0f9-29e3bb5dbe01.html
点击查看题目
157. What term is used for the amount of time an activity can be delayed from its early start without delaying the planned project finish date?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-9738-c0f9-29e3bb5dbe00.html
点击查看题目
14. In which of the following areas of management is payback analysis most likely to be used?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-7628-c0f9-29e3bb5dbe01.html
点击查看题目
76. What process group does the project integration management knowledge area map to through
the activities of developing project charters?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-f710-c0f9-29e3bb5dbe01.html
点击查看题目
135. In project schedule management, which is an output of controlling the schedule?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-6858-c0f9-29e3bb5dbe01.html
点击查看题目
114. Which document should list and describe all of the deliverables required for the project?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-4148-c0f9-29e3bb5dbe00.html
点击查看题目
95. An organizational process assets update is the output of which closing process?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-1a38-c0f9-29e3bb5dbe01.html
点击查看题目
150. Which is one of the main outputs of estimating activity resources process?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-8798-c0f9-29e3bb5dbe01.html
点击查看题目
179. What do people who seek to excel and tend to avoid both low-risk and high-risk situations to
improve their chances for achieving something worthwhile have a high need for?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-be48-c0f9-29e3bb5dbe01.html
点击查看题目
199. In the Tuckman model, what occurs as team members have different opinions as to how the
team should operate?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-e558-c0f9-29e3bb5dbe00.html
点击查看题目
首页
>
IT互联网
>
项目管理期末复习WJH
题目内容
(
单选题
)
手机预览
试题通
项目管理期末复习WJH

70. What processes include defining and authorizing a project or project phase?

A、 Initiating

B、 Planning

C、 Executing

D、 Monitoring and controlling

答案:A

试题通
分享
试题通
试题通
项目管理期末复习WJH
相关题目
181. According to McClelland’s acquired-needs theory, what do people who want to direct others,
and can be seen as bossy, have a need for?

A.  affiliation

B.  advancement

C.  power

D.  achievement

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-c230-c0f9-29e3bb5dbe01.html
点击查看答案
157. What term is used for the amount of time an activity can be delayed from its early start without delaying the planned project finish date?

A.  total slack

B.  free float

C.  Backward pass

D.  forward pass

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-9738-c0f9-29e3bb5dbe00.html
点击查看答案
14. In which of the following areas of management is payback analysis most likely to be used?

A.  Resource

B.  Communication

C.  Cost

D.  Quality

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-7628-c0f9-29e3bb5dbe01.html
点击查看答案
76. What process group does the project integration management knowledge area map to through
the activities of developing project charters?

A.  initiating

B.  planning

C.  Executing

D.  monitoring and controlling

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-f710-c0f9-29e3bb5dbe01.html
点击查看答案
135. In project schedule management, which is an output of controlling the schedule?

A.  activity duration estimate

B.  project management plan update

C.  activity attribute

D.  milestones list

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-6858-c0f9-29e3bb5dbe01.html
点击查看答案
114. Which document should list and describe all of the deliverables required for the project?

A.  project charter

B.  scope statement

C.  WBS

D.  Gantt chart

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-4148-c0f9-29e3bb5dbe00.html
点击查看答案
95. An organizational process assets update is the output of which closing process?

A.  project integration management

B.  project quality management

C.  project procurement management

D.  project time management

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-1a38-c0f9-29e3bb5dbe01.html
点击查看答案
150. Which is one of the main outputs of estimating activity resources process?

A.  project documents update

B.  milestone list

C.  breakdown structure

D.  activity duration estimate

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-8798-c0f9-29e3bb5dbe01.html
点击查看答案
179. What do people who seek to excel and tend to avoid both low-risk and high-risk situations to
improve their chances for achieving something worthwhile have a high need for?

A.  affiliation

B.  security

C.  power

D.  achievement

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-be48-c0f9-29e3bb5dbe01.html
点击查看答案
199. In the Tuckman model, what occurs as team members have different opinions as to how the
team should operate?

A.  performing

B.  norming

C.  forming

D.  storming

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-e558-c0f9-29e3bb5dbe00.html