31. Which attribute is true of low-end tools of project management software?

A、 They are designed for especially large projects with multiple users.

B、 Their main advantage is that they have unlimited functionality.

C、 They provide basic project management features.

D、 They are referred to as enterprise project management software.

答案:C

项目管理期末复习WJH
113. Which task is at the lowest level of the WBS?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-3d60-c0f9-29e3bb5dbe01.html
点击查看题目
30. Which of the following refers to a set of principles that guides decision making based on personal values of what is considered right and wrong?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-9568-c0f9-29e3bb5dbe01.html
点击查看题目
106. Which action involves normalizing acceptance of the project deliverables and during this phase the key project stakeholders, such as the customer and sponsor for the project, inspect and then formally accept the deliverables?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-31a8-c0f9-29e3bb5dbe00.html
点击查看题目
89. Which planning process is associated with project scope management?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-0e80-c0f9-29e3bb5dbe01.html
点击查看题目
108. Which output documents how project needs will be analyzed, documented, and managed?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-3590-c0f9-29e3bb5dbe00.html
点击查看题目
159. Which technique involves doing activities in parallel that one would normally do in sequence?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-9738-c0f9-29e3bb5dbe02.html
点击查看题目
143. Which dependencies involve relationships between project and non-project activities?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-77f8-c0f9-29e3bb5dbe01.html
点击查看题目
177. Who is best known for distinguishing between motivational factors and hygiene factors when
considering motivation in work settings?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-ba60-c0f9-29e3bb5dbe01.html
点击查看题目
115. Which approach for constructing a WBS uses a similar project’s WBS as a starting point?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-4148-c0f9-29e3bb5dbe01.html
点击查看题目
191. What term is used for taking time to renew oneself physically, spiritually, mentally and socially?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-d5b8-c0f9-29e3bb5dbe01.html
点击查看题目
首页
>
IT互联网
>
项目管理期末复习WJH
题目内容
(
单选题
)
手机预览
项目管理期末复习WJH

31. Which attribute is true of low-end tools of project management software?

A、 They are designed for especially large projects with multiple users.

B、 Their main advantage is that they have unlimited functionality.

C、 They provide basic project management features.

D、 They are referred to as enterprise project management software.

答案:C

分享
项目管理期末复习WJH
相关题目
113. Which task is at the lowest level of the WBS?

A.  variance

B.  objective

C.  deliverable

D.  work package

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-3d60-c0f9-29e3bb5dbe01.html
点击查看答案
30. Which of the following refers to a set of principles that guides decision making based on personal values of what is considered right and wrong?

A.  Ethics

B.  Civics

C.  Laws

D.  Politics

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-9568-c0f9-29e3bb5dbe01.html
点击查看答案
106. Which action involves normalizing acceptance of the project deliverables and during this phase the key project stakeholders, such as the customer and sponsor for the project, inspect and then formally accept the deliverables?

A.  Creating scope

B.  Defining scope

C.  Controlling scope

D.  Validating scope

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-31a8-c0f9-29e3bb5dbe00.html
点击查看答案
89. Which planning process is associated with project scope management?

A.  Collecting requirements

B.  Performing qualitative risk analysis

C.  Planning schedule management

D.  Estimating costs

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-0e80-c0f9-29e3bb5dbe01.html
点击查看答案
108. Which output documents how project needs will be analyzed, documented, and managed?

A.  requirements traceability matrix

B.  requirements management plan

C.  WBS

D.  project scope statement

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-3590-c0f9-29e3bb5dbe00.html
点击查看答案
159. Which technique involves doing activities in parallel that one would normally do in sequence?

A.  Critical chain scheduling

B.  Crashing

C.  Fast tracking

D.  PERT analysis

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-9738-c0f9-29e3bb5dbe02.html
点击查看答案
143. Which dependencies involve relationships between project and non-project activities?

A.  mandatory

B.  discretionary

C.  external

D.  inherent

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-77f8-c0f9-29e3bb5dbe01.html
点击查看答案
177. Who is best known for distinguishing between motivational factors and hygiene factors when
considering motivation in work settings?

A.  Frederick Herzberg

B.  David McClelland

C.  Abraham Maslow

D.  Douglas McGregor

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-ba60-c0f9-29e3bb5dbe01.html
点击查看答案
115. Which approach for constructing a WBS uses a similar project’s WBS as a starting point?

A.  top-down

B.  bottom-up

C.  mind-mapping

D.  analogy

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-4148-c0f9-29e3bb5dbe01.html
点击查看答案
191. What term is used for taking time to renew oneself physically, spiritually, mentally and socially?

A.  empathic mirroring

B.  sharpening the saw

C.  synergizing

D.  thinking win/win

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-d5b8-c0f9-29e3bb5dbe01.html
点击查看答案