题目内容
(
单选题
)
18. A is a tool used in risk management.

A、 work breakdown structure

B、 project organizational chart

C、 critical path analysis

D、 probability matrix

答案:D

项目管理期末复习WJH
93. Which process includes measuring progress toward project objectives and taking corrective
action to match progress with the plan?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-1650-c0f9-29e3bb5dbe01.html
点击查看题目
200. In the Tuckman model, what occurs when the emphasis is on reaching the team goals, rather
than working on team process?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-e558-c0f9-29e3bb5dbe01.html
点击查看题目
188. Which type of power involves using punishment, threats, or other negative approaches to get
people to do things they do not want to do?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-d1d0-c0f9-29e3bb5dbe00.html
点击查看题目
150. Which is one of the main outputs of estimating activity resources process?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-8798-c0f9-29e3bb5dbe01.html
点击查看题目
75. The organization recognizes that a new project exists and completes a project charter during
which processes for a new project?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-f710-c0f9-29e3bb5dbe00.html
点击查看题目
109. Which process involves generating ideas by comparing specific project practices or product
characteristics to those of other projects or products inside or outside the performing organization?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-3590-c0f9-29e3bb5dbe01.html
点击查看题目
41. Grey’s Infotech sells customized hardware and software solutions for businesses. The
salespeople for Grey’s have a strict dress code when meeting clients. They are required to wear dark business suits, in order to convey the company’s dedication to quality. The meaning conveyed to the clients’ through the salespeople’s clothing is part of the frame of the organization.
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-acd8-c0f9-29e3bb5dbe00.html
点击查看题目
119. During which approach do team members first identify as many specific tasks related to the
project as possible and then aggregate the specific tasks and organize them into summary activities, or higher levels in the WBS?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-4918-c0f9-29e3bb5dbe01.html
点击查看题目
130. In project schedule management, which process generates the main outputs of an activity list,
activity attributes, and a milestone list?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-6088-c0f9-29e3bb5dbe00.html
点击查看题目
197. Which term refers to the amount of individual resources an existing schedule requires during
specific time periods?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-e170-c0f9-29e3bb5dbe00.html
点击查看题目
首页
>
IT互联网
>
项目管理期末复习WJH
题目内容
(
单选题
)
手机预览
项目管理期末复习WJH

18. A is a tool used in risk management.

A、 work breakdown structure

B、 project organizational chart

C、 critical path analysis

D、 probability matrix

答案:D

分享
项目管理期末复习WJH
相关题目
93. Which process includes measuring progress toward project objectives and taking corrective
action to match progress with the plan?

A.  Planning

B.  Monitoring and controlling

C.  Executing

D.  Initiating

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-1650-c0f9-29e3bb5dbe01.html
点击查看答案
200. In the Tuckman model, what occurs when the emphasis is on reaching the team goals, rather
than working on team process?

A.  performing

B.  norming

C.  forming

D.  storming

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-e558-c0f9-29e3bb5dbe01.html
点击查看答案
188. Which type of power involves using punishment, threats, or other negative approaches to get
people to do things they do not want to do?

A.  legitimate

B.  coercive

C.  reward

D.  referent

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-d1d0-c0f9-29e3bb5dbe00.html
点击查看答案
150. Which is one of the main outputs of estimating activity resources process?

A.  project documents update

B.  milestone list

C.  breakdown structure

D.  activity duration estimate

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-8798-c0f9-29e3bb5dbe01.html
点击查看答案
75. The organization recognizes that a new project exists and completes a project charter during
which processes for a new project?

A.  initiating

B.  planning

C.  opening

D.  controlling

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-f710-c0f9-29e3bb5dbe00.html
点击查看答案
109. Which process involves generating ideas by comparing specific project practices or product
characteristics to those of other projects or products inside or outside the performing organization?

A.  variance

B.  benchmarking

C.  prototyping

D.  Decomposition

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-3590-c0f9-29e3bb5dbe01.html
点击查看答案
41. Grey’s Infotech sells customized hardware and software solutions for businesses. The
salespeople for Grey’s have a strict dress code when meeting clients. They are required to wear dark business suits, in order to convey the company’s dedication to quality. The meaning conveyed to the clients’ through the salespeople’s clothing is part of the frame of the organization.

A.  political

B.  symbolic

C.  structural

D.  human resources

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-acd8-c0f9-29e3bb5dbe00.html
点击查看答案
119. During which approach do team members first identify as many specific tasks related to the
project as possible and then aggregate the specific tasks and organize them into summary activities, or higher levels in the WBS?

A.  analogy

B.  bottom-up

C.  top-down

D.  mind mapping

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-4918-c0f9-29e3bb5dbe01.html
点击查看答案
130. In project schedule management, which process generates the main outputs of an activity list,
activity attributes, and a milestone list?

A.  sequencing activities

B.  defining activities

C.  resource estimating activities

D.  estimating activity durations

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-6088-c0f9-29e3bb5dbe00.html
点击查看答案
197. Which term refers to the amount of individual resources an existing schedule requires during
specific time periods?

A.  resource loading

B.  resource leveling

C.  resource histogram

D.  resource logs

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-e170-c0f9-29e3bb5dbe00.html
点击查看答案