13. Fast tracking is an example of a tool used in management.

A、 schedule

B、 quality

C、 communication

D、 risk

答案:A

项目管理期末复习WJH
19. Which statement is true of project management?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-7df8-c0f9-29e3bb5dbe01.html
点击查看题目
138. Which term is used for a significant event on a project that normally has no duration?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-7028-c0f9-29e3bb5dbe00.html
点击查看题目
14. In which of the following areas of management is payback analysis most likely to be used?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-7628-c0f9-29e3bb5dbe01.html
点击查看题目
46. In what type of organizational structure do project managers have the least amount of authority?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-b890-c0f9-29e3bb5dbe00.html
点击查看题目
171. Which highly respected psychologist, rejected the dehumanizing negativism of psychology and proposed the hierarchy of needs theory?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-aea8-c0f9-29e3bb5dbe01.html
点击查看题目
175. What is at the top of Maslow’s hierarchy of needs?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-b678-c0f9-29e3bb5dbe01.html
点击查看题目
182. Which test presents subjects with a series of ambiguous pictures and asks them to develop a
spontaneous story for each picture, assuming they will project their own needs into the story?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-c618-c0f9-29e3bb5dbe00.html
点击查看题目
147. During which relationship is the “from” activity unable start until the “to” activity is started?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-7fc8-c0f9-29e3bb5dbe01.html
点击查看题目
91. Which are outputs of the executing process of project integration management?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-1268-c0f9-29e3bb5dbe01.html
点击查看题目
137. Which statement best describes the difference between an activity list and an activity attribute?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-6c40-c0f9-29e3bb5dbe01.html
点击查看题目
首页
>
IT互联网
>
项目管理期末复习WJH
题目内容
(
单选题
)
手机预览
项目管理期末复习WJH

13. Fast tracking is an example of a tool used in management.

A、 schedule

B、 quality

C、 communication

D、 risk

答案:A

分享
项目管理期末复习WJH
相关题目
19. Which statement is true of project management?

A.  It is a simple discipline with a limited scope.

B.  It has specific tools which work universally across all kinds of projects.

C.  It does not guarantee successes for all projects.

D.  Its framework consists solely of project management knowledge areas.

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-7df8-c0f9-29e3bb5dbe01.html
点击查看答案
138. Which term is used for a significant event on a project that normally has no duration?

A.  milestone

B.  activity attribute

C.  activity sequence

D.  schedule baseline

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-7028-c0f9-29e3bb5dbe00.html
点击查看答案
14. In which of the following areas of management is payback analysis most likely to be used?

A.  Resource

B.  Communication

C.  Cost

D.  Quality

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-7628-c0f9-29e3bb5dbe01.html
点击查看答案
46. In what type of organizational structure do project managers have the least amount of authority?

A.  Functional

B.  Project

C.  Matrix

D.  Circular

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-b890-c0f9-29e3bb5dbe00.html
点击查看答案
171. Which highly respected psychologist, rejected the dehumanizing negativism of psychology and proposed the hierarchy of needs theory?

A.  Sigmund Freud

B.  Abraham Maslow

C.  Carl Jung

D.  Philip Zimbardo

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-aea8-c0f9-29e3bb5dbe01.html
点击查看答案
175. What is at the top of Maslow’s hierarchy of needs?

A.  esteem

B.  self-actualization

C.  physiological

D.  social

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-b678-c0f9-29e3bb5dbe01.html
点击查看答案
182. Which test presents subjects with a series of ambiguous pictures and asks them to develop a
spontaneous story for each picture, assuming they will project their own needs into the story?

A.  RAM

B.  MBTI

C.  TAT

D.  RACI

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-c618-c0f9-29e3bb5dbe00.html
点击查看答案
147. During which relationship is the “from” activity unable start until the “to” activity is started?

A.  start-to-start

B.  finish-to-finish

C.  finish-to-start

D.  start-to-finish

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-7fc8-c0f9-29e3bb5dbe01.html
点击查看答案
91. Which are outputs of the executing process of project integration management?

A.  Deliverables

B.  Issue logs

C.  Resource calendars

D.  Enterprise environmental factor updates

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-1268-c0f9-29e3bb5dbe01.html
点击查看答案
137. Which statement best describes the difference between an activity list and an activity attribute?

A.  As opposed to an activity attribute, an activity list provides resource requirements and
constraints related to activities.

B.  An activity list provides a more concrete list of milestones for a project than an activity
attribute.

C.  An activity attribute is a tabulation of activities to be included on a project schedule
whereas an activity list is not.

D.  An activity attribute provides more schedule-related information about each activity than
an activity list.

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-6c40-c0f9-29e3bb5dbe01.html
点击查看答案
试题通小程序
试题通app下载