A、 making effective use of the people involved with the project.
B、 buying goods and services for a project from outside the performing organization.
C、 generating, collecting, disseminating, and storing project information.
D、 identifying and analyzing stakeholder
needs while managing and controlling their engagement.
答案:B
A、 making effective use of the people involved with the project.
B、 buying goods and services for a project from outside the performing organization.
C、 generating, collecting, disseminating, and storing project information.
D、 identifying and analyzing stakeholder
needs while managing and controlling their engagement.
答案:B
A. responsibility assignment matrix
B. resource histogram
C. RACI charts
D. organizational breakdown structure
A. creating the work breakdown structure
B. selecting the project manager
C. developing the project charter
D. identifying the project sponsor
A. initiating
B. planning
C. Executing
D. monitoring and controlling
A. Member identity
B. People focus
C. Group emphasis
D. Unit integration
A. planning
B. monitoring and controlling
C. closing
D. executing
A. project
B. symbolic
C. matrix
D. functional
A. It is a dependency in which the “from” activity cannot start until the “to” activity or
successor is started.
B. It is a dependency in which in which the “from” activity must finish before the “to”
activity or successor can start.
C. It is a dependency in which the “from” activity must be finished before the “to” activity
can be finished.
D. It is a dependency in which the “from” activity must start before the “to” activity can be
finished.
A. sequencing activities
B. defining activities
C. resource estimating activities
D. estimating activity durations
A. activity duration estimate
B. project management plan update
C. activity attribute
D. milestones list
A. Political frame
B. Symbolic frame
C. Structural frame
D. Human resources frame