题目内容
(
单选题
)
3. The role of a is to provide direction and funding for a project.

A、 project sponsor

B、 project manager

C、 support staff member

D、 project team

答案:A

项目管理期末复习WJH
86. What is the main purpose of project plans?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-0a98-c0f9-29e3bb5dbe01.html
点击查看题目
108. Which output documents how project needs will be analyzed, documented, and managed?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-3590-c0f9-29e3bb5dbe00.html
点击查看题目
2. Which objective is true of projects?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-5eb8-c0f9-29e3bb5dbe00.html
点击查看题目
62. Which systems development life cycle model assumes that requirements will remain stable after they are defined?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-dbb8-c0f9-29e3bb5dbe00.html
点击查看题目
85. What is one of the main outputs of the initiation process?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-0a98-c0f9-29e3bb5dbe00.html
点击查看题目
32. Which type of tool is usually recommended for small projects and single users?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-9950-c0f9-29e3bb5dbe01.html
点击查看题目
77. The project scope management knowledge area maps to which process group through the
activities of scope validation and scope control?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-faf8-c0f9-29e3bb5dbe00.html
点击查看题目
138. Which term is used for a significant event on a project that normally has no duration?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-7028-c0f9-29e3bb5dbe00.html
点击查看题目
84. Which is an example of a pre-initiation task?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-06b0-c0f9-29e3bb5dbe01.html
点击查看题目
129. Which process in project schedule management involves identifying the specific tasks that the project team members and stakeholders must perform to produce the project deliverables?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-5ca0-c0f9-29e3bb5dbe01.html
点击查看题目
首页
>
IT互联网
>
项目管理期末复习WJH
题目内容
(
单选题
)
手机预览
项目管理期末复习WJH

3. The role of a is to provide direction and funding for a project.

A、 project sponsor

B、 project manager

C、 support staff member

D、 project team

答案:A

分享
项目管理期末复习WJH
相关题目
86. What is the main purpose of project plans?

A.  schedule management plans

B.  define project scope

C.  estimate activity resources

D.  guide project execution

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-0a98-c0f9-29e3bb5dbe01.html
点击查看答案
108. Which output documents how project needs will be analyzed, documented, and managed?

A.  requirements traceability matrix

B.  requirements management plan

C.  WBS

D.  project scope statement

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-3590-c0f9-29e3bb5dbe00.html
点击查看答案
2. Which objective is true of projects?

A.  They have an indefinite beginning and end.

B.  They have a unique purpose.

C.  They are developed using regressive elaboration.

D.  They are permanent in nature.

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-5eb8-c0f9-29e3bb5dbe00.html
点击查看答案
62. Which systems development life cycle model assumes that requirements will remain stable after they are defined?

A.  Spiral life cycle

B.  Waterfall life cycle

C.  Prototyping life cycle

D.  RAD life cycle

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-dbb8-c0f9-29e3bb5dbe00.html
点击查看答案
85. What is one of the main outputs of the initiation process?

A.  creating the work breakdown structure

B.  selecting the project manager

C.  developing the project charter

D.  identifying the project sponsor

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-0a98-c0f9-29e3bb5dbe00.html
点击查看答案
32. Which type of tool is usually recommended for small projects and single users?

A.  Low-end

B.  Midrange

C.  High-end

D.  Upper range

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-9950-c0f9-29e3bb5dbe01.html
点击查看答案
77. The project scope management knowledge area maps to which process group through the
activities of scope validation and scope control?

A.  initiating

B.  planning

C.  Executing

D.  monitoring and controlling

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-faf8-c0f9-29e3bb5dbe00.html
点击查看答案
138. Which term is used for a significant event on a project that normally has no duration?

A.  milestone

B.  activity attribute

C.  activity sequence

D.  schedule baseline

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-7028-c0f9-29e3bb5dbe00.html
点击查看答案
84. Which is an example of a pre-initiation task?

A.  Drawing up a work breakdown structure

B.  Developing a business case for a project

C.  Drafting the project charter

D.  Identifying stakeholders

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-06b0-c0f9-29e3bb5dbe01.html
点击查看答案
129. Which process in project schedule management involves identifying the specific tasks that the project team members and stakeholders must perform to produce the project deliverables?

A.  defining activities

B.  sequencing activities

C.  developing the schedule

D.  estimating activity durations

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-5ca0-c0f9-29e3bb5dbe01.html
点击查看答案