AI智能推荐题库-试题通 AI智能整理导入题库-试题通
×
首页 题库中心 CPIM PART2-供应链资格认证考试 题目详情
C93BF00FBEF00001B89720C0D4CE1712
CPIM PART2-供应链资格认证考试
3,028
单选题

A company has started a total quality management program, WIP inventory most likely will:

A
Be unchanged
B
Be eliminated
C
Increase
D
Decrease

答案解析

正确答案:D

解析:

A TQM program is based on the participation of all members of an organization in improving processes, goods, services and the culture in which they work; As wastes and redundancies are removed from processes, one of the outcomes is that inventories will be reduced;
题目纠错
CPIM PART2-供应链资格认证考试

扫码进入小程序
随时随地练习

相关题目

单选题

Concurrent engineering is defined as which of the following approaches?

单选题

To decrease time to market for discrete products, it is most effective to improve which of the following phases?

单选题

An immediate benefit of implementing lean manufacturing improvement is:

单选题

Production activity control is essential to a closed-loop system because it:

单选题

Which of the following costing methods shows the greatest apparent profit in a time of inflation?

单选题

Which of the following performance metrics best measures customers satisfaction?

单选题

A supplier of roller bearing makes lots of 10000 and short them automatically according to size. In a typical lot of 1000, the sizes break into the categories: The product requires rollers on target or, at most, 0.0001 oversize. Experience indicated that 100% must be respected before use because the machine inspection lets a few defective units slip through. The supplier should be encouraged to take which of the following actions?

单选题

A work center has a balance between the scheduled input and output over the next 4 weeks. One of the 3 machines in the work center will be out of service for 1 week. Currently, 3 operators work the 1st shift, 1 operator works the 2nd shift, and each has a 40-hour work week. Which of the following actions is best to take to maintain the schedule?

单选题

Which of the following persons has direct responsibility for the accuracy of production activity reporting

单选题

To successfully implement a multiple-site pickup of parts from different supplier, it is necessary that:

关闭登录弹窗
专为自学备考人员打造
勾选图标
自助导入本地题库
勾选图标
多种刷题考试模式
勾选图标
本地离线答题搜题
勾选图标
扫码考试方便快捷
勾选图标
海量试题每日更新
波浪装饰图
欢迎登录试题通
可以使用以下方式扫码登陆
APP图标
使用APP登录
微信图标
使用微信登录
试题通小程序二维码
联系电话:
400-660-3606
试题通企业微信二维码