A gear manufacturer has departments running 3 shifts/day, 5 days a week except for the heat-treating furnace which must run 24 hours/day, 7 days a week;
Shifts for all departments, except the heat-treating furnace, are 8 hours with 1 hour of lunch/break time per day.
The heat-treating furnace produces 50 units/hour, operating 24 hours/day, 7 days/week, with no down time;
The gear machining process produces 85 units an hour, operating at 3 shifts/day, 5 days/week.
The final assembly line currently is a bottleneck and is capable of producing at a rate of 120 units per hour, and operates 1 shift/day, 5 days/week.
Demand is for 8000 end items per week, what actions should the company make that will allow the 8000 end items to be made?
答案解析
解析:
Gear machining currently produces 8925 units per week (5*3*7*85), therefore, it already produces enough for the 8000units/week;
Final assembly currently produces 4200 units per week (5*7*120), increasing the final assembly process to 2 shifts per day produces 8400 units per week, which can now handle the 8000 a week demand;
Once these changes are made, the 3 operations can make 8400, 8925 and 8400 respectively. The pace of production should be tuned to meet the 8000 a week demand;
相关题目
An executive discussion centers on offshoring and outsourcing. Prior to the outsourcing discussion it would be best to invite the Director of
Supply chain variation frequently occurs when
A market leader in systems computing failed to adapt to market trends for smaller devices and cloud computing. This reveals a poor assessment process concerning their
Establishing a result-oriented, high performance culture generally requires managers and other leaders to
The 2 different types of performance targets that should be used to achieve organizational stretch objectives are
When a company has multiple divisions essentially performing the same functions, a good first step related to continuous improvement and benchmarking would be
Failure to meet customer expectations with order qualifiers will likely
Attending a seminar where a person from a competing company reveals how they improved part & raw materials inventory turns is an example of
A primary shortcoming of using the payback period method to justify capital budgeting expenditure is
Of the 5 popular and commonly used capital budget techniques, 4 common methods are: