Internal setup time: 1 hour
external setup time: 2 hours
queue time: 8 hours
run time per 1000 units: 8 hours
move time: 2 hours
standard cost per hour: $60
standard material cost per unit: $10
standard allocated overhead per hour: $30.00
The standard cost to produce one unit based on a batch qty of 1000 is
答案解析
解析:
相关题目
In the sales and operations planning process, the responsibility for the finished goods inventory levels belongs to
An indication on the sales and operations plan of a MTS company that a chase production strategy is being employed is
A production leveling strategy refers to
Which of the following key resources is most likely to be used to validate the production plan in a high-volume company that produces a number of families of windows, including standard and custom sizes, and unique design?
Manufacturing is responsible for executing which of the plans that come from the sales and operations planning meeting?
The production planning process uses which of the following time fences?
Stockouts have occurred to failures by suppliers to ship on schedule, causing extensive backorders. The past due orders were successfully reduced due to overtime once the parts arrived. The best approach for incorporating this information into the sales and operations planning process for the upcoming month is to
One reason for evaluating multiple sales and operations plans during the pre-S&OP meeting is
Which of the following production strategies should show the most consistently high capacity performance?
Which of the following actions will a company most likely take as a primary focus of their level production strategy to deal with demand peaks while meeting standard lead time delivery?