Early customer involvement in the design process can result in
答案解析
解析:
相关题目
Which of the following are objectives of the master schedule?
I. A level repeating schedule
II. Changes are kept to a minimum
III. The schedule sums to the production plan
IV. Maintain planning bills
Which of the following statements are true regarding the final assembly schedule?
I. It is a statement of the exact set of end products to be built.
II. It controls the manufacturing from fabricated products to shippable products.
III. It schedules the purchase of components not under MPS control which are needed for final assembly.
The rough-cut capacity plan will differ from the resource plan in which of the following ways?
I. The rough-cut capacity plan is less detailed than the resource plan.
II. The rough-cut capacity plan considers more production resources.
III. Lead times are offset in the rough-cut capacity plans.
IV. Rough-cut plans are displayed in months or quarters.
In which of the following environments will the final assembly schedule normally correspond to the MPS?
I. Make-to-stock
II. Make-to-order
III. Assemble-to-order
The major advantage of a two level MPS process is which of the following?
Which of the following will result from the level strategy of production planning?
I. Production occurs at exactly the same rate as the sales forecast for each period.
II. Inventory will generally build.
III. The labor force and capacity usage remains stable.
Which of the following are included in a closed loop MRP system?
I. Master Production Scheduling
II. Capacity Requirement Planning
III. Purchasing
Period: 1 2 3 4 5
Forecast: 10 10 10 20 20
Orders: 8 6 6 2 2
PAB
MPS 30 0 0 0 0
On Hand 20
Based on the above MPS record, what is the non-cumulative ATP in Period 1?
Which of the following pieces of information must be available in order to prepare a realistic MPS?
I. Knowledge of all production requirements
II. Available capacity
III. Load profile of each MPS item
Which of the following statements are true regarding production planning?
I. It is senior management's responsibility.
II. The master scheduler should "disaggregate" the production plan to the master schedule.
III. It focuses corporate production goals.