Cooperation between partners within a supply chain can best be achieved by setting up multiple channels of
答案解析
解析:
相关题目
There are many obstacles to implementing JIT in a manufacturing environment. Which of the following obstacles would be considered most difficult to overcome?
Traditional measurements of manufacturing are not as useful in the flow manufacturing environment. Which of the following would be good measures to use?
I. Machine utilization
II. Defect rates
III. Setup times
Which of the following can be considered factors in the success of an SGIA?
I. Management support and commitment
II. Clear goals always established by management
III. Educating and training all personnel
IV. Recognizing and rewarding the group
The time required between the completion of each successive end product is called:
Under full absorption costing, indirect costs would be handled by which of the following methods?
Which of the following are true regarding variable costing?
I. Fixed factory overhead is not assigned to the product
II. It is acceptable for external financial reporting
III. It is beneficial for internal analysis
Based on the following information, what is the lost time factor?
Planned hours 10
Standard hours earned 8
Actual hours worked 10
In product A, the standard amount of material to be used is 20 units. After running yesterday, 22 units were used to produce product A. The 2 extra units needed are known as a(an):
WORK CENTER 210 (in standard hours)
Period 1 2 3 4 5
PLANNED INPUT 150 150 150 150 150
ACTUAL INPUT 150 145 130
Period 1 2 3 4 5
PLANNED OUTPUT 180 180 180 180 150
ACTUAL OUTPUT 185 140 160
Based on the input/output control chart above, in which period was the input/output rule broken?
WORK CENTER 210 (in standard hours)
Period 1 2 3 4 5
PLANNED INPUT 150 150 150 150 150
ACTUAL INPUT 150 145 130
Period 1 2 3 4 5
PLANNED OUTPUT 180 180 180 180 150
ACTUAL OUTPUT 185 140 160
Based on the input/output control chart above, what should the input be in Period 4 in order to reduce the backlog?