In a company that regularly has a past due order condition backward scheduling in MRP and forward scheduling in an ATO environment have what in common?
答案解析
解析:
Start dates and required dates may not be the same based on the dates used to begin the scheduling process; The critical path is generally the same, but may be different due to the overload condition;
相关题目
In the Kaizen process, goals should be established which are:
Which of the following best describes transcendent quality?
Which of the following is most critical to the success of supply chain alliances?
The most effective way for a manager to develop a project budget is to use:
The main purpose of an AS/RS system is to:
According to Whitney, business units lose focus for all the following reasons EXCEPT:
The integrated production of all the technical data needed to design, manufacture, test and support a product best defines which of the following?
The measure of how easy it is to return a product or machine to functional condition after it has failed is known as:
The purpose of a Steering Committee in a JIT implementation is to:
I. Approve and recommend projects
II. Ensure resources are available
III. Revise priorities
IV. Be primary "cheerleaders"
According to Hamel in his article, "Strategy as Revolution," there are three constituencies that are underrepresented but need to be included in the strategy setting process. Which of the following is one of the constituencies?