In the Kaizen process, goals should be established which are:

A
stretch goals (50%)
B
incremental improvements (5%).
C
quality of life goals (improve the cafeteria).
D
educational improvements.

答案解析

正确答案:A

解析:

Kaizen events are meant to make dramatic improvements of at least 50%. Incremental improvements of 5% will not provide any competitive advantage because the industry is changing so fast. Without stretch goals, the team will only improve what the objective is set at. If the objective, for example, is to reduce the set up by 10%, then the team will stop when that goal has been reached.
CPIM PART2-供应链资格认证考试

扫码进入小程序
随时随地练习

相关题目

单选题

In a company that regularly has a past due order condition backward scheduling in MRP and forward scheduling in an ATO environment have what in common?

单选题

The following information is available for a work center on day 8. The start date and end days are based solely on internal setup and run time. Based on the critical ratio. Which of the following jobs is the next to be started?
Job Start work day End work day
W 11 14
X 10 15
Y 8 12
Z 9 12

单选题

Which of the following actions minimizes or eliminates wasteful activities in an operation?

单选题

Which 2 of the following approaches to product design most positively impact manufacturing performance?
1. Reducing parts complexity
2. Organizing design processes
3. Debugging during the manufacturing cycle
4. Integrating product and process design

单选题

A company monitors production by knowing that is in process and what the queue time is. Average run time is 1 hour and queue time are kept fairly uniform by the planning and scheduling process. Jobs are produced in First in, First out sequence. Which of the following information is earlier for monitoring purposes in this scenario?

单选题

A job shop environment includes

单选题

Actual queue time of a job at a work center is most impacted by the

单选题

A potential process transition point that a business with declining production volume may face is

单选题

Increasing lead times in an effort to get more work done and meet the schedule will most likely result in

单选题

Identifying sources for procurement regardless of location is an example of

关闭登录弹窗
专为自学备考人员打造
勾选图标
自助导入本地题库
勾选图标
多种刷题考试模式
勾选图标
本地离线答题搜题
勾选图标
扫码考试方便快捷
勾选图标
海量试题每日更新
波浪装饰图
欢迎登录试题通
可以使用以下方式扫码登陆
APP图标
使用APP登录
微信图标
使用微信登录
试题通小程序二维码
联系电话:
400-660-3606
试题通企业微信二维码