Which of the following criteria would management be most likely to ignore when establishing performance measures for master scheduling?

A
Order shipped on time and complete per the MPS
B
Necessity of a feasible production plan since it is only an approximation of production
C
Necessity that product resource profiles used in RCCP be accurate
D
Impact of forecast accuracy on the ability to match the master schedule with the production plan

答案解析

正确答案:D

解析:

Regardless of the source of demand, the master schedule must aggregate to the production plan, this is part of the MPS process and does not need to be measured;
CPIM PART2-供应链资格认证考试

扫码进入小程序
随时随地练习

关闭登录弹窗
专为自学备考人员打造
勾选图标
自助导入本地题库
勾选图标
多种刷题考试模式
勾选图标
本地离线答题搜题
勾选图标
扫码考试方便快捷
勾选图标
海量试题每日更新
波浪装饰图
欢迎登录试题通
可以使用以下方式扫码登陆
APP图标
使用APP登录
微信图标
使用微信登录
试题通小程序二维码
联系电话:
400-660-3606
试题通企业微信二维码