A company produces a line of configurable desks shipped from retailers. Orders are taken at the store and transmitted to the factory daily with delivery promised within 5 to 10 work days, depending on the options. This is achieved by stocking drawers, desk subassemblies and hardware. Which of the following master schedule formats is best for this product family?

A
2-level
B
single-level
C
multi-level
D
one-level

答案解析

正确答案:A

解析:

two-level would allow the use of a super bill to plan options and key subassemblies in configure-to-order environment;
A single-level master schedule is a statement of what the company expects to produce based on the tactical plan and budget constraints;
Multi-level master schedules support ATO production and delivery;
CPIM PART2-供应链资格认证考试

扫码进入小程序
随时随地练习

关闭登录弹窗
专为自学备考人员打造
勾选图标
自助导入本地题库
勾选图标
多种刷题考试模式
勾选图标
本地离线答题搜题
勾选图标
扫码考试方便快捷
勾选图标
海量试题每日更新
波浪装饰图
欢迎登录试题通
可以使用以下方式扫码登陆
APP图标
使用APP登录
微信图标
使用微信登录
试题通小程序二维码
联系电话:
400-660-3606
试题通企业微信二维码