AI智能推荐题库-试题通 AI智能整理导入题库-试题通
×
首页 题库中心 CPIM PART2-供应链资格认证考试 题目详情
C93BF00FBEF00001B89720C0D4CE1712
CPIM PART2-供应链资格认证考试
3,028
单选题

In a company that has over 20,000 end items in stock, which of the following demand elements is likely to take the most time to assess for sales and operations planning?

A
Demand for hedge inventory
B
Demand for existing products
C
Demand for a sales promotion
D
Demand for a new product

答案解析

正确答案:B

解析:

Demand must be determined the product families in aggregate, a single new product can be fairly easily added to the existing families;
CPIM PART2-供应链资格认证考试

扫码进入小程序
随时随地练习

相关题目

单选题

In the master scheduling process, customer orders are the only source of demand in periods

单选题

Which of the following tradeoffs should be considered to improve the performance of a distribution network?

单选题

A company wanting to maintain a high level of customer service at the lowest inventory carrying cost should place safety stock in:

单选题

Which of the following goals is the primary outcome of distribution requirements planning?

单选题

Which of the following actions is part of the pre-sales and operations planning meeting?

单选题

A Canadian-based company has a long-term contract with a US-based supplier. The Canadian company has been experiencing short shipments and variations of the supply lead time with the US supplier for a few months. Which of the following is the most
appropriate action for the master production scheduler in this situation?

单选题

Distribution requirements planning would most directly interface with:

单选题

The question below is based on the following production environment information: In which facility would product unit costs most likely be reduced through a setup reduction program?
Facility A Facility B Facility C Facility D
Product volume High High Lower Lower
Product variety High Lower High Lower
Production LT Long Short Long Short
Operation/product Many Few Many Few
Production resources Many Many Few Few

单选题

The question below is based on the following distribution requirements plan: Lead time is 1 week, lot size is 30, and safety stock is 0. Planned order releases would occur in which of
the following sequences?
Period 1 2 3 4 5 6
Gross requirements 20 15 18 23 26 27
Scheduled receipt 30
PAB 12

单选题

The following question is based on the following information: The master production schedule quantity that should be placed in Period 7 is:
Lead time=0 Lot size=20
DTF=0 PDF=4
On hand=10 SS=3
Period 1 2 3 4 5 6 7 8 9
Forecast 10 10 15 10 10 5 10 10 15
Customer PO 5 2 1
MPS 20 20 20

关闭登录弹窗
专为自学备考人员打造
勾选图标
自助导入本地题库
勾选图标