In an MTO environment, what is most likely to be used to convert product demand into MRP over the planning horizon?
It is important for a material planner to know which of the following demand information from the MPS?
A purchased component has a net requirements in period 4. It has a 6-period lead time and no schedule receipts. Which of the following actions would be the result of MRP?
Which of the follow statements is true about the MRP process?
A company produces a variety of items with short manufacturing lead times. Which of the following capacity planning techniques would be most useful for bottle neck work center?
Consolidated information stored in a single record that contain everything needed to know about a part to plan it effectively is referred to as
Increasing planned lead times will result in which of the following outcomes?
Input
Period 1 2 3 4 5 6
Plan 400 400 450 450 500 500
Actual 450 430 440 480 520 530
Output
Period 1 2 3 4 5 6
Plan 400 400 450 450 500 500
Actual 360 410 530 460 520 540
Using the information provided, what was the WIP at the end of period 4 if it was 35 prior to period 1?
Which of the following elements is used to reduce system nervousness?
Which of the following is typically a significant benefit of using bar coded labels to identify parts and storage locations?