Which of the following packing slip errors most likely indicated that there are 2 errors?
Period 1 2 3 4 5 6 7 8
Gross requirements 40 10 30 50 50 20 30 40
Scheduled receipts
Projected available 130
order quantity: 40
Safety stock: 10
Lead time: 3 periods
What is the first period where a planned order receipt is the result of dipping into the safety stock?
A supplier has notified the buyer at an order for a component will be 2 weeks late due to a material shortage. Which of the following actions should the material planner take?
Which of the following outputs from MRP is of most use to the rest of the organization for achieving the material plan?
Using a planning horizon shorter than the longest cumulative lead time may result in
A firm planned order is used to
Significant reductions in which of the following lead times has the most positive impact on material planning?
The plan for the production and purchase of components used in making items in the MPS is the
Period 1 2 3 4 5 6 7 8
Gross requirements 22 28 0 20 0 32 22 24
Scheduled receipts 0 40
Projected available 24
lead time=1 week
Order policy: lot for lot
what is the planned order release in period 5?
A component has 3 qualified suppliers, but none has been designated as the primary supplier, which of the following lead times should be used for MRP in order to ensure delivery reliability?