Sometimes, the more distant suppliers will absorb the additional freight charge to match the freight charge of the geographically closer supplier. This practice is known as:

A
freight equalization
B
freight consolidation
C
freight dissemination
D
freight socialization

答案解析

正确答案:A

解析:

Freight equalization eliminates the competitive advantage of lower freight charges the nearer supplier has.
CPIM PART2-供应链资格认证考试

扫码进入小程序
随时随地练习

相关题目

单选题

A scheduling method for compressing lead time or to expedite a small quantity is

单选题

Infinite loading will indicate which of the following situations when comparing a gateway work center to a non-gateway non-bottleneck operation?

单选题

Which of the following elements of lead time is ignored by CRP?

单选题

In a job shop environment, which situation is optimal from a capacity planning perspective?

单选题

Theoretical capacity is most closely approached by

单选题

Which of the following actions would result in shorter purchasing lead times?

单选题

An ETO environment with fairly long lead times has a severely overloaded work center in the middle of the production process. Assuming deadlines cannot be changed, a simulation of the situation is most likely to

单选题

Infinite loading is useful for

单选题

Which of the following flows is most likely used in a flow environment that is supply-constrained by the availability of a seasonal vegetable?

单选题

A textile plant spins fiber into yarn, weaves yarn into a line of standard fabrics, and dyes these fabrics to custom-color specifications. Dyeing is done in a light-to-dark sequence to reduce high changeover costs. While spinning and dyeing capacity is adequate during the peak season, the capacity of the plant's weaving operations is well below the required level. If product design and price are the primary competitive factors, which two of the following actions would effectively resolve the problem?
1. Building inventory of feed yarn just before the peak season begins;
2. Building inventory of undyed fabric just before the peak season begins;
3. Changing weaving and dyeing schedules to accommodate the needs of key customers
4. Changing weaving schedules to use subcontractors during the peak season;

关闭登录弹窗
专为自学备考人员打造
勾选图标
自助导入本地题库
勾选图标
多种刷题考试模式
勾选图标
本地离线答题搜题
勾选图标
扫码考试方便快捷
勾选图标
海量试题每日更新
波浪装饰图
欢迎登录试题通
可以使用以下方式扫码登陆
APP图标
使用APP登录
微信图标
使用微信登录
试题通小程序二维码
联系电话:
400-660-3606
试题通企业微信二维码