Which of the following best describes one of the difficulties in controlling traditional engineering activities?

A
Lack of engineering support personnel
B
No common engineering and manufacturing schedule
C
Not enough engineers for the project
D
Too much manufacturing involvement

答案解析

正确答案:B

解析:

Gillen and Robidoux write that, "because of the separation of engineering activities from manufacturing, it is difficult in traditional engineering to establish a common schedule. Typically, scheduling starts by presenting a need date to engineering."
CPIM PART2-供应链资格认证考试

扫码进入小程序
随时随地练习

相关题目

单选题

A company operates a strict pull system with their suppliers with shipments every 2, 4 and 8 hours. A 3rd party logistics supplier manages all incoming and outgoing shipments. Which of the following delivery performance measures is most likely to incorporate a tolerance to allow for uncontrolled conditions?

单选题

A primary reason for using an alternative means of transportation when a part is late is

单选题

2 suppliers for a new part have responded to a request for quote based on annual usage projection. The buyer is evaluating the suppliers on total cost criteria. With all things generally equal otherwise, which of the following reasons best explains why total cost is higher for one supplier?

单选题

The design of a product is improved by which of the following factors?
1. Identification of process similarities;
2. Evaluation of standard part attributes;
3. Input from the supplier;

单选题

A technique useful for businesses to become virtual supply chains in order to reduce costs and improve due-date performance is

单选题

An action that most limits the effect of changes on a supplier is

单选题

On-time supplier deliveries can be impacted most by

单选题

Which of the following elements is a key principle of lean purchasing?

单选题

A supplier is on site counting and restocking inventory, this is referred to as

单选题

Which of the following production environments is likely to have the most supplier partnerships where product life cycle is a considerations?

关闭登录弹窗
专为自学备考人员打造
勾选图标
自助导入本地题库
勾选图标
多种刷题考试模式
勾选图标
本地离线答题搜题
勾选图标
扫码考试方便快捷
勾选图标
海量试题每日更新
波浪装饰图
欢迎登录试题通
可以使用以下方式扫码登陆
APP图标
使用APP登录
微信图标
使用微信登录
试题通小程序二维码
联系电话:
400-660-3606
试题通企业微信二维码