There are times when a project needs to be shortened. Shortening a project by assigning more resources to one or more of the critical activities is called:
答案解析
解析:
相关题目
Which of the following aspects of a job most determined the day and time when it will be done?
In a job shop environment, which lead time element is typically the longest?
Central point scheduling is a technique that
Which of the following situations is most likely a reason for establishing order priorities with a FAS based on internal measures, rather than on customer-oriented measures?
Which of the following orders will production have the most of for planning and scheduling in an ATO environment?
For a product that has moved from regular production to spare parts supply, which of the following factors is likely to become LEAST important?
It is determined that it is not possible to complete all the jobs at the work center on time. To solve the problem, the dispatcher removes the job which will take the longest and reschedules it so that the remaining jobs will be completed on time. This sequencing techniques is an example of
A work cell has 6 operations, information required to determine the capacity of the cell includes
Production has determined that a particular order will be late due to a purchased part being pass due. Which of the following scenarios is most likely to occur in a job shop environment?
Which of the following manufacturing processes most likely would be characterized by a narrow range of standard product, lower direct labor costs and a high level of technical support for manufacturing?