The manufacturing operation has just picked an unplanned issue for the current operation. The unplanned issue has occurred due to scrap, which was unexpected. The cost of the unplanned issue, in a standard cost system, will be charged to:

A
material price variance
B
usage variance
C
volume variance
D
purchase price variance

答案解析

正确答案:B

解析:

A usage variance is recorded when the actual usage of materials is greater than the standard material usage required. If there is continuing unplanned issues for this component(s), then further investigation would be needed. It may be that the standard quantity is inaccurate or the operation cannot be completed with the standard quantity.
题目纠错
CPIM PART2-供应链资格认证考试

扫码进入小程序
随时随地练习

关闭登录弹窗
专为自学备考人员打造
勾选图标
自助导入本地题库
勾选图标
多种刷题考试模式
勾选图标
本地离线答题搜题
勾选图标
扫码考试方便快捷
勾选图标
海量试题每日更新
波浪装饰图
欢迎登录试题通
可以使用以下方式扫码登陆
APP图标
使用APP登录
微信图标
使用微信登录
试题通小程序二维码
联系电话:
400-660-3606
试题通企业微信二维码