单选题

Which of the following factors typically has the largest effect on the schedule developed by an advanced production scheduling (APS) system?

A
Priorities of the master schedule items
B
Amount of past due work
C
Performance measures used
D
Precision of the capacity data

答案解析

正确答案:A
题目纠错
CPIM PART2-供应链资格认证考试

扫码进入小程序
随时随地练习

相关题目

单选题

Which of the following statement about pyramid forecasting in most accurate?

单选题

Which of the following methods is most likely to be used to prioritize problems to be addressed?

单选题

In an attempt to reduce costs associated with information system transaction, which of the following approaches should be considered?
I. Backflushing component issues
II. Reducing levels in the BOM
III. Using EDI to transmit orders to suppliers
IV. Reducing lot sizes of manufactured products

单选题

In discrete manufacturing, CRP receives which two of the following items from MRP:
I. Due dates
II. Order quantities
III. Standard hours
IV. Low-level codes

单选题

What functions may be directly involved in developing and maintaining customer-supplier relationships?
1. Purchasing department
II. Product engineering
III. Quality management
IV. Human resources

单选题

Which two of the following conditions describe and environment that most likely will support change successfully?
I. The CEO spearheads the change process
II. The organization is under considerable internal or external pressure to improve;
III. Major projects are tackled first to achieve maximum benefit;
IV. Experimentation is accepted as a part of the change process;

单选题

Which of the following tools is best for identifying quality problems for a process?

单选题

DRP serves which of the following purposes in the marketplace?

单选题

Barriers to overcome in developing a lean customer relationship include the customer's fear of which of the following situations?
I. Sharing proprietary data
II. Missing delivery dates
III. Having a single-source supplier
IV. Having to install an EDI system

单选题

Within an approach using both JIT and TQC, what is the role of TQC?

关闭登录弹窗
专为自学备考人员打造
勾选图标
自助导入本地题库
勾选图标
多种刷题考试模式
勾选图标
本地离线答题搜题
勾选图标
扫码考试方便快捷
勾选图标
海量试题每日更新
波浪装饰图
欢迎登录试题通
可以使用以下方式扫码登陆
APP图标
使用APP登录
微信图标
使用微信登录
试题通小程序二维码
联系电话:
400-660-3606
试题通企业微信二维码