单选题

The MOST significant impact of electronic business on supply chain management is what?

A
Coordination information
B
Electronic date interface
C
Electronic Kanban
D
Reduction of paper products

答案解析

正确答案:A
题目纠错
CPIM PART2-供应链资格认证考试

扫码进入小程序
随时随地练习

相关题目

单选题

Arrranging for some suppliers to replenish frequently is small lots is a likely outcome from a task created to

单选题

The bill of distribution defines the:

单选题

Which of the following is not a component of a demand pattern?

单选题

When investing in large, high-throughput equipment the planned tradeoff is typically between reduced unit costs and the potential of

单选题

Which of the following inventory evaluation methods best measures falling costs

单选题

Information technology investment approvals and proof of payback are uniquely difficult due to the fact that

单选题

Which of the following methods is the most effective way for the supervisor to help a group generate new ideas?

单选题

Which of the following actions should a design engineering staff take to improve product performance and quality for a company adding new options for a product line?

单选题

Which of the following distribution lead time elements is a determinants of when a truck is loaded during the daily schedule for delivery of goods to a particular store?

单选题

A medium-sized, MTO manufacturing company has three operating divisions and four locations, with three plants in one country and one plant in another country. The second largest divisions was a recent acquisition. There are there different software packages in use at the plants, and each plant has its own way of operating its business. The overall costs per transaction for the company are the highest in its industry. Senior management has decided that the plants should standardize on one software packaging and one approach to all major business processes to achieve some economies of scale. A new software package is selected and a project leader named. The new project leader has assembled a team to perform the implementation. For the change to be effective, senior management should first:

关闭登录弹窗
专为自学备考人员打造
勾选图标
自助导入本地题库
勾选图标
多种刷题考试模式
勾选图标
本地离线答题搜题
勾选图标
扫码考试方便快捷
勾选图标
海量试题每日更新
波浪装饰图
欢迎登录试题通
可以使用以下方式扫码登陆
APP图标
使用APP登录
微信图标
使用微信登录
试题通小程序二维码
联系电话:
400-660-3606
试题通企业微信二维码