A、 The environment has an availability target of 99.5% for all infrastructure
B、 The recovery time objective (RTO) for Tier 1 virtual machines is one hour
C、 Access to the management cluster within the environment must be controlled
D、 Windows and Linux virtual machines must reside on separate clusters
答案:C
A、 The environment has an availability target of 99.5% for all infrastructure
B、 The recovery time objective (RTO) for Tier 1 virtual machines is one hour
C、 Access to the management cluster within the environment must be controlled
D、 Windows and Linux virtual machines must reside on separate clusters
答案:C
A. Host profiles must be used for this kind of installation
B. Scratch partition would need to be created on the external storage
C. The size of the SD cards is too small and the installation will fail
D. The vSphere Auto Deploy feature must be enabled on vCenter Server
A. Maximum tolerable downtime
B. Predicted platform growth
C. Auditing requirements for the virtual machines
D. The level of isolation required between virtual machine classifications
A. The virtual infrastructure environment must connect application virtual machines and management services to new physical network switches
B. The virtual infrastructure environment must connect application virtual machines and management services to separate distributed virtual switches (DVS)
C. The virtual infrastructure environment must connect application virtual machines and management services to separate VLANs
D. The virtual infrastructure environment must connect management services to a vSphere standard switch (VSS)
A. Use Route Based on Physical NIC Load
B. Use Network I/O Control with Shares.
C. Use Network I/O Control with Reservation.
D. Use Link Aggregation Control Protocol (LACP).
E. Use Network I/O Control with Limits.
A. Two
B. Three
C. One
D. None
A. Use an SSO domain across all vCenter Server instances
B. Use an SSO domain per region
C. Use an SSO domain per vCenter Server instance
D. Use an SSO domain per site
A. Two 1 GbE network adapters per server
B. Four 1 GbE network adapters per server
C. Four 10 GbE network adapters per server
D. Two 10 GbE network adapters per server
A. The manufacturer and model of the CPUs in the hosts
B. The amount of capacity available for failover of virtual machines within the cluster
C. The downtime allowed for virtual machines that will be running within the cluster
D. The cost to procure and maintain the hardware
E. The number of virtual machines that will be running within the cluster
A. Leave the newly acquired company’s assets in its current place
B. Lift and shift the acquired assets into the data center.
C. Migrate the acquired company’s virtual machines into the existing vSphere environment.
D. Migrate and apply vSphere tags to the acquired company’s virtual machines.
REQ01: The customer is looking for a way to limit database virtual machine (VM ) placement to save on CPU licensing costs.
CON01: There is a single cluster with no budget to scale.
CON02: All virtual machines must run on the consolidated cluster.
Which two design decisions should the architect make to meet the customer requirement? Choose two.
A. The solution must use VM-VM anti-affinity rules
B. The solution must use vSphere DRS in manual mode
C. The solution must use a vRealize Orchestrator workflow for VM placement
D. The solution must use VM-Host affinity rules
E. The solution must use vSphere VM and host DRS groups