Machine operators at XYZ company are paid on an incentive system. Production is reported by the operator, including scrap. No adjustment is made for parts found defective at final inspection. Verification of parts counts is not routinely done. Which of the following outcomes would be expected in this environment?
1. Reported parts counts would tend to be higher than actual
2. The value of WIP inventory would be understated
3. Scrapped parts would tend not to be reported
答案解析
解析:
2 is incorrect because incentive production results in high WIP inventories as operators select products with high process yields and long production runs;
相关题目
What is the direct reflection of planned and actual lead time?
If customer demand is 250 a week and production available is 40 hours a week, what is the takt time?
An Aluminum supplier uses time period safety stock concept. Their policy is to have a half of a week's protection. Their current demand is 1000 units a week. The next period they forecast they will sell 750 units. How many units most be produced in the second time period?
Which of the following are inputs to Capacity Requirements Planning?
1. MRP
2. Work centers
3. Routing
4. Capacity requirement plan
What type of engineer is their function to produce a product at the right quality economically and consistently?
When looking at BOM, under APICS rules, assembly part numbers are shown as what?
Which of the following would be included in the item master file?
1. Manufacturing lead time
2. Quantity on order
3. Safety stock
4. Balance on hand
What type of scheduling uses a particular operation to schedule from?
Company ABC trying to calculate how much safety stock they should have for their highest selling product. With the follow information calculate the safety stock.
Standard deviation=25
Safety factor=4.00
Lead time=4 weeks
Forecast of 250 per week
Which of the following are basic methods of managing a contract?
1. Vendor scheduling
2. Direct shipment
3. Release system