An information system implementation project is 6 months behind schedule because many people involved with the project are working on a serious problem with product quality. Which of the following actions should the executive steering committee take in this situation?
答案解析
解析:
The project manager will not have enough power to get the project restarted. Turning the project over to a third party is a very negative option that does not get to the root of the problem;
Cancelling a project underway is a very expensive and negative solution. It will usually mean the cancellation of company strategies based on the anticipated utilization and efficiencies arising out of the implementation;
相关题目
Michelle's diaper company is trying to determine the target inventory level for their best selling diapers. With the information below, what is the target inventory level?
Lead time = 2 weeks
Forecast = 40 per week
Review period = 4 weeks
Safety stock = 50
What captures and defines the work activities, deliverables and timeline a vendor will execute against in performance of specified work for a customer?
A PAST DUE message would be what type of MRP message?
For a MTS environment, when the part has passed final inspection and booked to stores it becomes what?
Operating scheduling is most effective when
1. Plant makes to work orders
2. Routings are complex and variable
3. There are sequencing rules
All of the following are included in the work center file EXCEPT
What type of BOM is used to manage by-products?
What are the 3 areas of simulation?
1. Lot order sizing
2. MRP as a simulator
3. "What if" facility
4. Linear programming
What has a demand pattern with large flu cations from one time period to another?
The look a head period is determined by what?