AI智能推荐题库-试题通 AI智能整理导入题库-试题通
×
首页 题库中心 CPIM PART2-供应链资格认证考试 题目详情
C93BF00FBEF00001B89720C0D4CE1712
CPIM PART2-供应链资格认证考试
3,028
单选题

An information system implementation project is 6 months behind schedule because many people involved with the project are working on a serious problem with product quality. Which of the following actions should the executive steering committee take in this situation?

A
Let the project manager handle the program and get the project back to schedule
B
Reschedule implementation efforts based on the resources currently available
C
Contract with an outside systems and consulting group to implement the system
D
Cancel the system implementation because it is adversely affecting product family

答案解析

正确答案:B

解析:

The executive sponsors of the project need to get the project restarted, this will probably mean that schedule dates, cots and resources will need to be changed from the original plan;
The project manager will not have enough power to get the project restarted. Turning the project over to a third party is a very negative option that does not get to the root of the problem;
Cancelling a project underway is a very expensive and negative solution. It will usually mean the cancellation of company strategies based on the anticipated utilization and efficiencies arising out of the implementation;
题目纠错
CPIM PART2-供应链资格认证考试

扫码进入小程序
随时随地练习

关闭登录弹窗
专为自学备考人员打造
勾选图标
自助导入本地题库
勾选图标
多种刷题考试模式
勾选图标
本地离线答题搜题
勾选图标
扫码考试方便快捷
勾选图标
海量试题每日更新
波浪装饰图
欢迎登录试题通
可以使用以下方式扫码登陆
APP图标
使用APP登录
微信图标
使用微信登录
试题通小程序二维码
联系电话:
400-660-3606
试题通企业微信二维码