单选题

The purpose of first article inspection is to verify the product's

A
Sustainability
B
Manufacturability
C
Functionality
D
Process variability

答案解析

正确答案:B
CPIM PART2-供应链资格认证考试

扫码进入小程序
随时随地练习

相关题目

单选题

In an assemble-to-order company with many final configurations, few subassemblies, and many components, good master scheduling practices would include:

单选题

A company manufactures products which have many low level components, a few subassemblies, and a large number of final configurations. Good master scheduling practices would include:

单选题

All of the following may contribute to an unrealistic master production schedule except:

单选题

Which of the following best describes the term synchronization to the production plan

单选题

A company with a cumulative lead time of 13 weeks to manufacture has a planning horizon of 11 weeks. Which of the following will occur?
I. Order releases for suppliers will occur without sufficient lead time.
II. Constant expediting will occur.
III. Manufacturing inefficiencies will be created.

单选题

Rough cut capacity planning helps to identify all of the following EXCEPT:

单选题

The master production schedule is an input to MRP because of which of the following attributes?
I. It provides a rough cut capacity plan
II. It is a time phased schedule of production items

单选题

Companies which master schedule at the end item level are:

单选题

Capacity utilization is calculated as:

单选题

Which of the following are key elements in defining available-to-promise?
I. It is uncommitted future inventory or capacity.
II. It is calculated from the MPS.
III. It is used for customer order promising.
IV. It is used in make-to-stock and assemble-to-order companies.

关闭登录弹窗
专为自学备考人员打造
勾选图标
自助导入本地题库
勾选图标
多种刷题考试模式
勾选图标
本地离线答题搜题
勾选图标
扫码考试方便快捷
勾选图标
海量试题每日更新
波浪装饰图
欢迎登录试题通
可以使用以下方式扫码登陆
APP图标
使用APP登录
微信图标
使用微信登录
试题通小程序二维码
联系电话:
400-660-3606
试题通企业微信二维码