If it is assumed that final products and lower level assemblies are made to order and to stock, which of the following FAS practices should be adopted?
In an assemble-to-order company with many final configurations, few subassemblies, and many components, good master scheduling practices would include:
A company manufactures products which have many low level components, a few subassemblies, and a large number of final configurations. Good master scheduling practices would include:
All of the following may contribute to an unrealistic master production schedule except:
Which of the following best describes the term synchronization to the production plan
A company with a cumulative lead time of 13 weeks to manufacture has a planning horizon of 11 weeks. Which of the following will occur?
I. Order releases for suppliers will occur without sufficient lead time.
II. Constant expediting will occur.
III. Manufacturing inefficiencies will be created.
Rough cut capacity planning helps to identify all of the following EXCEPT:
The master production schedule is an input to MRP because of which of the following attributes?
I. It provides a rough cut capacity plan
II. It is a time phased schedule of production items
Companies which master schedule at the end item level are:
Capacity utilization is calculated as: