Which of the following project documents describes the purpose, history, deliverables, and measurable success indicators for a project?

A
Work breakdown structure
B
Statement of work
C
Scope statement
D
Milestone schedule

答案解析

正确答案:B

解析:

A project's statements of work is one of the first planning documents that should be prepared, it describes the purpose, history, deliverables and measurable success indicators for a project;
The milestone schedule provides an estimated timeline for the life of the project. ... The schedule should include milestones for the planning, development, construction, evaluation and reporting of the project's implementation. The milestone dates are only projected dates based on an anticipated grant award.
Milestone schedule is incorrect because includes only a high-level schedule displaying important deliverables;
The scope statement is limited to describing the products to be created by the project;
The WBS is a hierarchical description of the project including project phases, deliverables and work packages;
CPIM PART2-供应链资格认证考试

扫码进入小程序
随时随地练习

相关题目

单选题

In a properly designed MRP system, which of the following objectives can be achieved?
I. Provide input to the capacity requirement planning module.
II. Maintain open order priorities.
III. Manage inventories properly.

单选题

Performance measures for senior managers need to be multidimensional. Which of the following best describes a multidimensional performance measure?

单选题

Tasks within and across small work groups are called:

单选题

When creating measurements, what seems to be the maximum number of measures per criteria? (e.g. Flexibility, Quality, etc)

单选题

Traditional cost systems focus on capturing direct material and direct labor costs while summarizing all other costs as a percentage of the direct labor hours. While this method of accounting conforms to GAAP (generally accepted accounting principles) accounting standards, it does not provide the necessary information for managers to effectively run their operations. Which of the following is one of the reasons traditional accounting is not useful to measure operations?

单选题

Some companies have been using a measure of profitability for their business which takes after tax profit minus the total cost of capital. The total cost of capital includes equipment, real estate, computers and other equipment which should improve productivity plus working capital such as cash , inventories and receivables. This calculation and profitability measure is known as:

单选题

Comparing the relative effectiveness of two or more businesses in performing a process by comparing the cost to perform and the level of success in execution is called:

单选题

A project justification has two objectives. One is to validate the need for the acquisition of the new technology. The second is to

单选题

Using a PERT network to manage projects generally involves a high degree of time uncertainty. To further clarify this uncertainty, the PERT team looked at time as a random variable to which statistics could be applied. Which of the following is not a time estimate to be used in solving the statistical probability of time during a project?

单选题

All of the following are functions of supply chain management EXCEPT:

关闭登录弹窗
专为自学备考人员打造
勾选图标
自助导入本地题库
勾选图标
多种刷题考试模式
勾选图标
本地离线答题搜题
勾选图标
扫码考试方便快捷
勾选图标
海量试题每日更新
波浪装饰图
欢迎登录试题通
可以使用以下方式扫码登陆
APP图标
使用APP登录
微信图标
使用微信登录
试题通小程序二维码
联系电话:
400-660-3606
试题通企业微信二维码