Orders that provides the supplier with forward visibility of the requirements for a component are called

A
open orders
B
blanket orders
C
Firm planned orders
D
Planned orders

答案解析

正确答案:B
CPIM PART2-供应链资格认证考试

扫码进入小程序
随时随地练习

相关题目

单选题

What equals direct time charged/ clock time scheduled?

单选题

A shop worker performs a task which has a standard time of 12 hours and he finishes in 10 hours. This same worker during this same time was only supposed to work an 8 hour shift, but ended up working a 10 hour shift to help get the project done early. Calculate the rated capacity for a standard 40 hour week using the above job as a baseline?

单选题

The Indoor Store presents the following facts pertaining to the cost of one product carried in its merchandise inventory:
Beginning inventory on hand, 200 units @ $15 = $3,000
Purchase June 1, 200 units @$16 = $3,200
Purchase July 5, 200 units @ $20 = $4,000
Purchase August 25, 200 units @ $25 = $5,000
A new order comes in for 500 units. What is the cost of goods sold that should be recorded using a simple weighted average using the LIFO methodology?

单选题

The difference between a master schedule and a master production schedule is that master production schedule is what?

单选题

Actual lead time is directly affected by what?

单选题

To track a shipment without manual inspection would include which of the following
I. RFID
II. EDI
III. Bar Codes
IV. Poka Yoke

单选题

All of the following are techniques to reduce lead time EXCEPT

单选题

A purchase order is signed with ABC company for $3,000 worth of materials. The average salary of a buyer is paid $25 an hour and manufacturing gets paid $20 an hour.
It takes 5 hours for a buyer to set up a purchase order and it takes manufacturing 10 hours to set up the job and 40 hours to process the job
How much are the ordering/ setup costs for this purchase order?

单选题

What is defined as the amount of planned work scheduled for and actual work released to a facility, work center, or operation for a specific span of time?

单选题

Who should be the only people to make an engineering change request?

关闭登录弹窗
专为自学备考人员打造
勾选图标
自助导入本地题库
勾选图标
多种刷题考试模式
勾选图标
本地离线答题搜题
勾选图标
扫码考试方便快捷
勾选图标
海量试题每日更新
波浪装饰图
欢迎登录试题通
可以使用以下方式扫码登陆
APP图标
使用APP登录
微信图标
使用微信登录
试题通小程序二维码
联系电话:
400-660-3606
试题通企业微信二维码