相关题目
If customer demand is 100 a day and production available is 8 hours, what is the takt time?
When using MRP, which of the following are NOT a discrete ordering method?
I. Period Order Quantity
II. Periodic Ordering
III. Fixed Order Quantity
IV. Quantity Ordering
Which of the following is NOT a finite loading technique?
If a company has the following framework, what is MOST LIKELY manufacturing environment?
1. Produces standard products
2. Orders raw materials based on forecast of total sales
The following are critical measures of performance to link design to manufacturing performance EXCEPT
All of the following are objectives of cycle counting EXCEPT
Shortage lists, hot lists and top ten lists are all ways to help enable what?
A Final Assembly schedule is a schedule of end items to finish specific customer orders in what type of environment(s)?
I. Engineer to Order
II. Make to Order
III. Assemble to Order
IV. Make to Stock
All of the following are order approaches for procurement and delivery of materials and services EXCEPT
When a parent code is entered and all its contents displayed would be called what?