AI智能推荐题库-试题通 AI智能整理导入题库-试题通
×
首页 题库中心 CPIM PART2-供应链资格认证考试 题目详情
C93BF00FBEF00001B89720C0D4CE1712
CPIM PART2-供应链资格认证考试
3,028
单选题

The lead time used in DRP is

A
Transit time to the warehouse
B
Order fulfillment lead time
C
Manufacturing lead time
D
Delivery lead time

答案解析

正确答案:A
CPIM PART2-供应链资格认证考试

扫码进入小程序
随时随地练习

相关题目

单选题

If an operation on a routing is performed out of sequence and the change in sequence is not reported to the formal system, which of the following situation will occur?

单选题

A supplier of roller bearing makes lots of 10,000 and sorts them automatically according to size. In a typical lot of 10,000, the sizes break into the categories: The product requires rollers on target or, at most, 0.0001 oversize. Experience indicates that 100% must be respected before use because the machine inspection lets a few defective units slip through. The supplier should be encouraged to take which of the following actions?

单选题

When an order in split into two orders, the immediate effect on a job shop work center is to increase which of the following elements?

单选题

The average length of time a job must wait at a work center is a function of the:

单选题

A work center has one machine that is operated for one shift per day. The shop runs an 8-hour shift 5 days per week. Machine utilization has been 60% with efficiency at 80%. A routing through this work center has a standard run time of .10 hours per piece. Job number 1234 is for 200 pieces. If the utilization is improved to 80%, the difference in calculated lead time for the job is how many days?

单选题

Which of the following steps should be first in determining operation start dates for capacity planning?

单选题

The utilization of a downstream no bottleneck resource is determined by:

单选题

A work center has a balance between the scheduled input and output over the next 4 weeks. One of the 3 machines in the work center will be out of service for 1 week. Currently, 3 operators work the 1st shift, 1 operator works the 2nd shift, and each has a 40-hour work week. Which of the following actions is best to take to maintain the schedule?

单选题

Which if the following statements about the MRP due date for a shop order is true?

单选题

Which of the following persons has direct responsibility for the accuracy of production activity reporting

关闭登录弹窗
专为自学备考人员打造
勾选图标
自助导入本地题库
勾选图标
多种刷题考试模式
勾选图标
本地离线答题搜题
勾选图标
扫码考试方便快捷
勾选图标
海量试题每日更新
波浪装饰图
欢迎登录试题通
可以使用以下方式扫码登陆
APP图标
使用APP登录
微信图标
使用微信登录
试题通小程序二维码
联系电话:
400-660-3606
试题通企业微信二维码