AI智能推荐题库-试题通 AI智能整理导入题库-试题通
×
首页 题库中心 CPIM PART2-供应链资格认证考试 题目详情
C93BF00FBEF00001B89720C0D4CE1712
CPIM PART2-供应链资格认证考试
3,028
单选题

The top level of the DRP record should be

A
At the distribution center
B
At the manufacturing facility
C
At the MPS
D
At the point closest to the customer

答案解析

正确答案:D
CPIM PART2-供应链资格认证考试

扫码进入小程序
随时随地练习

相关题目

单选题

The implementation of a program designed to reduce changeover times will result in a temporary capacity shortage. This shortage will be handled by using some older equipment and by subcontracting some work. Which of the following methods should the company use to control capacity during this period?

单选题

Statistical process control is a technique primarily used to

单选题

Which of the following project characteristic would suggest using the PERT technique, rather than the critical path method?

单选题

The actual output of a work center for a given time period can be determined by evaluating the:

单选题

In a continuous flow environment, it is necessary to report which of the following data from the shop floor?

单选题

If an operation on a routing is performed out of sequence and the change in sequence is not reported to the formal system, which of the following situation will occur?

单选题

A supplier of roller bearing makes lots of 10,000 and sorts them automatically according to size. In a typical lot of 10,000, the sizes break into the categories: The product requires rollers on target or, at most, 0.0001 oversize. Experience indicates that 100% must be respected before use because the machine inspection lets a few defective units slip through. The supplier should be encouraged to take which of the following actions?

单选题

When an order in split into two orders, the immediate effect on a job shop work center is to increase which of the following elements?

单选题

The average length of time a job must wait at a work center is a function of the:

单选题

A work center has one machine that is operated for one shift per day. The shop runs an 8-hour shift 5 days per week. Machine utilization has been 60% with efficiency at 80%. A routing through this work center has a standard run time of .10 hours per piece. Job number 1234 is for 200 pieces. If the utilization is improved to 80%, the difference in calculated lead time for the job is how many days?

关闭登录弹窗
专为自学备考人员打造
勾选图标
自助导入本地题库
勾选图标
多种刷题考试模式
勾选图标
本地离线答题搜题
勾选图标
扫码考试方便快捷
勾选图标
海量试题每日更新
波浪装饰图
欢迎登录试题通
可以使用以下方式扫码登陆
APP图标
使用APP登录
微信图标
使用微信登录
试题通小程序二维码
联系电话:
400-660-3606
试题通企业微信二维码