单选题

Which of the following statements about production planning is true?

A
The production plan should be frozen for at least the cumulative lead time of the products
B
Production planning should be processed on a weekly basis and in detail by unique end items
C
Production plan families are broken down into MRP items and the time frame changed to days or weeks
D
Production planning is a process a company uses to plan its resources to change either backlog and/or finished goods inventory;

答案解析

正确答案:D

解析:

Planning should be done on a monthly or quarterly basis by product group or family and be broken down into MPS items
CPIM PART2-供应链资格认证考试

扫码进入小程序
随时随地练习

相关题目

单选题

A firm uses the level production planning approach to produce a product family to stock.
Senior management has requested that the finished-goods inventory for the product family
be reduced by 18% over the sales and operations planning horizon. Which of the following
statements best describes the relationship between total demand and total production
required for the product family over the planning horizon?

单选题

Which of the following inputs to the demand planning phase of sales and operations
planning typically is most important for a product line that is made to customer order?

单选题

In a make-to-order environment, if cumulative production exceeds cumulative demand,
which of the following outcomes will result?

单选题

The greatest risk of aggregating product families at too high of a level for sales and
operations planning is that:

单选题

Which of the following forecasting methods is most appropriate for projecting demand for a
product family?

单选题

Sales and operations planning in a make-to-stock environment is concerned with projecting

单选题

Production is being planned to emphasize the utilization of a critical and very expensive
piece of capital equipment. Which of the following production planning strategies should be
used?

单选题

In an assemble-to-order environment, which of the following indicators is most appropriate
for measuring the effectiveness of the master scheduling process?

单选题

If the master production schedule is overstated, which of the following short-term actions is most appropriate?

单选题

In a capacity-constrained situation, which of the following actions is best to take if marketing wants to increase production of a master schedule item?

关闭登录弹窗
专为自学备考人员打造
勾选图标
自助导入本地题库
勾选图标
多种刷题考试模式
勾选图标
本地离线答题搜题
勾选图标
扫码考试方便快捷
勾选图标
海量试题每日更新
波浪装饰图
欢迎登录试题通
可以使用以下方式扫码登陆
APP图标
使用APP登录
微信图标
使用微信登录
试题通小程序二维码
联系电话:
400-660-3606
试题通企业微信二维码