Period J F M A M J J A S O N D
Sales plan 50 50 60 60 80 90 70 50 40 40 40 40
Actual sales 51 48 64
Period J F M A M J J A S O N D
Production plan 50 60 60 70 70 70 70 50 50 50 50 40
Actual production 48 61 60
Period J F M A M J J A S O N D
Backlog plan 30 20 20 20 20 40 40 40 30 20 10 10
Actual backlog 30
What's the actual March backlog based on the information provided?
答案解析
相关题目
During which of the following process steps of sales and operations planning would resource planning be carried out?
Which of the following considerations is most important when selecting forecasting software?
A firm manufactures four product families in a single facility using one production line for each product family. It has selected the hybrid approach to production planning and has specified that there will be no more than four changes in production rates per production line in a year. Resource planning will have to be performed for:
Which of the following items is required for making realistic customer promises?
Which of the following criteria is used to determine safety stock in a distribution center?
Which of the following costs is most likely to decrease when the number of warehouses in a distribution network increases?
The question below is based on the distribution center requirements shown below: How many units of product X should be planned to satisfy the demand for period 6?
Lead time=2 periods
Lot size=20
SS=20
PD Period
1 2 3 4 5 6
Forecast 40 10 30 60 50 80
PAB 50 30 20 30 30
Planned receipt 20 0 40 60
Planned orders 40 60
A single-level, centralized distribution network would be most appropriate for a firm whose products are:
In a make-to-stock environment, which of the following factors is a key determinant of inventory levels necessary to support customer demand?
Which of the following objectives is a critical performance measurement in distribution network logistics?