Which of the following are documents created during the planning Phase?
I. Implementation document
II. Project schedule
III. Responsibility Assignment Matrix
IV. Work Breakdown Structure
答案解析
解析:
1. Statement of Work (SOW)
2. Work Breakdown Structure (WBS)
3. Project Schedule
4. Responsibility Assignment Matrix
5. Resource Requirements and Budget.
The implementation document is not created until the implementation phase of the project
相关题目
An executive discussion centers on offshoring and outsourcing. Prior to the outsourcing discussion it would be best to invite the Director of
Supply chain variation frequently occurs when
Which component control strategy can help mitigate the bullwhip effect when implemented properly?
Insourcing describes the decision to
A company that chooses to implement increases in existing manufacturing capacity in anticipation of demand is following
When the company is pursuing a capacity lead strategy it
A primary shortcoming of using the payback period method to justify capital budgeting expenditure is
Off the 5 popular and commonly used capital budget techniques, 4 common methods are:
By approving projects that improve the company's performance with their order qualifiers, the company is
A true statement about benchmarking is that it