单选题

If additional man-power is needed during the free-slack period of a project, what is the impact to the delivery time for that project?

A
Decreased costs
B
Complete earlier than scheduled
C
Complete later than scheduled
D
No change

答案解析

正确答案:D

解析:

If additional man-power is needed during the free-slack period of a project there would not be a change to the overall project schedule because it was in the free slack period time.
Free slack period is not on the critical task so can wait and use extra resources during that time with no effect to the
schedule.
CPIM PART2-供应链资格认证考试

扫码进入小程序
随时随地练习

相关题目

单选题

In the sales and operations planning process, the responsibility for the finished goods inventory levels belongs to

单选题

A form of exponential smoothing in which the smoothing constant is automatically adjusted as part of forecast error measurement is

单选题

A discrete manufacturer's marketing strategy is to be the low-cost, high-quality, high-volume, rapid-delivery supplier. Which of the following manufacturing processes would best fulfill this marketing strategy?

单选题

In an ETO company, which of the following criteria would be essential for the use of RCCP?
1. Education of user and management on capacity management concept;
2. Successful implementation of a material requirements planning system;
3. Accurate WIP inventory and finished goods;
4. A method of associating planned production with the amount of capacity required;

单选题

To prevent management from getting out of touch from what is really happening in the company, many CEO's ask leader to

单选题

Traditional understanding of managing risk in general typically identifies which of the following strategic risk response?

单选题

The strategic risk plan much have go/on-go guidelines for

单选题

The ultimate effect of a suggested change is strategy

单选题

It is determined that the key to success in a particular market is in the company's ability to deliver a variety of high quality products in less lead time than industry standard. The operational emphasis should be on the operation's

单选题

One of the purposes of generating and rewarding the short-term performance improvements within an organizational change is because this

关闭
专为自学备考人员打造
试题通
自助导入本地题库
试题通
多种刷题考试模式
试题通
本地离线答题搜题
试题通
扫码考试方便快捷
试题通
海量试题每日更新
试题通
欢迎登录试题通
可以使用以下方式扫码登陆
试题通
使用APP登录
试题通
使用微信登录
xiaochengxu
联系电话:
400-660-3606
xiaochengxu