According to Davis- what are the biggest problems of major implementations?
I. Not a strong project manager
II. Conflicting interpretations of business goals
III. Uncoordinated choosing and implementation of changes

A
I & III Only
B
II & III Only
C
I & II Only
D
I, II, & III

答案解析

正确答案:B

解析:

2 biggest problems of major implementation Davis
1. Conflicting interpretations of business goals
2. Uncoordinated choosing and implementation of changes
CPIM PART2-供应链资格认证考试

扫码进入小程序
随时随地练习

相关题目

单选题

Use of which two of the following techniques best supports the planning needs of an ATO manufacturer that produces a product with many options and whose order winner is delivery speed?
1. Safety lead time for finished goods
2. Safety stock of finished products
3. Safety stock for long lead time components
4. Planning bills that overplan options

单选题

Which production environment will most benefit from CTP functionality?

单选题

Which of the following products is most likely to be the simplest to develop a sales and operations plan for?

单选题

Long range forecasts typically use which of the following forecasting techniques?

单选题

Which of the following processes employs a finite scheduling model of a company's manufacturing system to determine when an item can be delivered?

单选题

The 1st step to be produced in the planning of the scheduling of goods and services is

单选题

A forecast technique used to define the relationship between two or more variables, used to predict one variable over another is

单选题

Period 1 2 3 4 5 6 7 8
Forecast 10 10 10 10 10 10 10 10
Customer PO 10 11 9 11 8 11 9 8
PAB 15 5 34 24 13 33 22 12 32
ATP
MPS 40 30 30
Using the information provided, what are the available to promise quantities for periods one through five?

单选题

Which of the following results is most indicated in the information provided regarding customer service levels?
Dec Jan Feb Mar
Sales plan 40 50 50 60
Actual sales 38 51 47 64
Difference -2 1 -3
Cumulative differences -2 -1 -4

Production plan 50 50 60 60
Actual production 40 48 60 60
Difference -10 -2 0
Cumulative differences -10 -12 -12

Backlog plan 40 30 30 20 20
Actual backlog 38 41 28
Difference 8 11 8

单选题

A critical issue for management to control in forecasting is

关闭
专为自学备考人员打造
试题通
自助导入本地题库
试题通
多种刷题考试模式
试题通
本地离线答题搜题
试题通
扫码考试方便快捷
试题通
海量试题每日更新
试题通
欢迎登录试题通
可以使用以下方式扫码登陆
试题通
使用APP登录
试题通
使用微信登录
xiaochengxu
联系电话:
400-660-3606
xiaochengxu