If a company has a capacity shortfall due to a machine shortage, what is the quickest and most effective way to maximize the capacity constraint?
答案解析
解析:
the machine. This maximizes the use of the machine without needing to hire or subcontract out some of the work.
相关题目
The next step in the planning hierarchy after the business plan is the
Which of the following statements is true of the relationship between the production plan and the resource plan?
Subassemblies and options need to be master scheduled separately from the end item in which of the following environments?
Which of the following interfaces deals primarily with translating monetary units into product families for planning purposes?
Period J F M A M J J A S O N D
Sales plan 50 50 60 60 80 90 70 50 40 40 40 40
Period J F M A M J J A S O N D
Production plan 50 60 60 70 70 70 70 50 50 50 50 40
Period J F M A M J J A S O N D
Inventory plan 20 30 30 40 30 10 10 10 20 30 40 40
What is the most likely reason for having any inventory in June in the information provided?
Period 1 2 3 4 5 6 7 8
Forecast 20 21 20 22 24 262 28 28
Customer PO 19 20 21 21 25 24 20 18
PAB 20
ATP
MPS 50 50 50 50
Using the information provided, what is the available to promise quantity in period 2?
Collaborating with customers to provide forecast information result in
The finite-scheduling model to determine when an item can be delivered to a customer that includes any constraints that might restrict production is
In which of the following production environment is it most unlikely that planning bills are used for master scheduling?
A company produces hats which can be personalized with logos. Delivery is quoted as ten days from receipt of the order. Which of the following sales and operations planning elements is most likely to be of little use to management?