Which of the following are principles of re-engineering?
I. Link parallel activities instead of integrating results
II. Put a decision point where work is performed
III. Capture info once at the source
IV. Treat geographically dispersed resources separately
答案解析
解析:
1. Organize around outcomes, not tasks
2. Have those that use the output of the process perform the process
3. Subsume info processing work into the real work that produces info
4. Treat geographically dispersed resources as they are centralized
5. Link parallel activities instead of integrating results
6. Put decision point where work is performed, and build control into the process
7. Capture info once at the source
相关题目
The average of a group of value is the
Forecast information used in the sales and operations planning process is updated
The sales forecast is disaggregate into individual forecasts at the distribution center level. This may result in
Which of the following types of production environments is most likely to have customer, forecast and distribution demand?
The next step in the planning hierarchy after the business plan is the
Which of the following statements is true of the relationship between the production plan and the resource plan?
Subassemblies and options need to be master scheduled separately from the end item in which of the following environments?
Which of the following interfaces deals primarily with translating monetary units into product families for planning purposes?
Period J F M A M J J A S O N D
Sales plan 50 50 60 60 80 90 70 50 40 40 40 40
Period J F M A M J J A S O N D
Production plan 50 60 60 70 70 70 70 50 50 50 50 40
Period J F M A M J J A S O N D
Inventory plan 20 30 30 40 30 10 10 10 20 30 40 40
What is the most likely reason for having any inventory in June in the information provided?
Period 1 2 3 4 5 6 7 8
Forecast 20 21 20 22 24 262 28 28
Customer PO 19 20 21 21 25 24 20 18
PAB 20
ATP
MPS 50 50 50 50
Using the information provided, what is the available to promise quantity in period 2?