A company has an effective sales and operations planning (S&OP) process with monthly plans over a 24 month horizon. The sales and marketing functions have requested that a new product introduction be moved from the tenth month to the sixth month of the current plans which would require a 10% increase in production for months six through nine. Which of the following actions would be the most appropriate next step in response to the request?

A
Reject the request to move the new product release in
B
Request reduction in other demand plans to offset the request
C
Incorporate the request into the current plan
D
Refer the request to the Executive S&OP meeting.

答案解析

正确答案:B
CPIM PART2-供应链资格认证考试

扫码进入小程序
随时随地练习

相关题目

单选题

Using the information provided, how many employees are needed to accomplish the planned production?
Beginning inventory 250
Total annual forecast demand 60,000
Ending inventory target 250
Working days per month 20
Number of periods 12
Employee productivity 25 per day

单选题

Which of the following production method is most likely to be sued in an ETO environment?

单选题

Which of the following actions to improve the validity of the master schedule is most under the master scheduler's control?

单选题

A company is changing from a MTO to ATO environment. Which of the following areas will likely change the most?

单选题

Which of the following process choices is likely to simplify the sales and operations planning process?

单选题

A forecast technique which uses average demand for a certain number of periods prior to the month being forecasted is

单选题

Which of the following techniques is best for relating one set of forecast economic data to another set of economic date?

单选题

The creation of a high-volume product with large variety so that a customer may specify an exact model is

单选题

Finish goods inventory states there are 100 items in stock, when there are actually 110. The first 100 customer orders are accepted and scheduled for immediate shipment. The next 50 customer orders are scheduled and promised for shipment the following week based on the next scheduled receipt. What is the customer service level for the orders scheduled for shipment?

单选题

The forecast of the previous month was 300, and the actual demand was 320, using a alpha factor of 0.3, what is the forecast for the new month?

关闭登录弹窗
专为自学备考人员打造
勾选图标
自助导入本地题库
勾选图标
多种刷题考试模式
勾选图标
本地离线答题搜题
勾选图标
扫码考试方便快捷
勾选图标
海量试题每日更新
波浪装饰图
欢迎登录试题通
可以使用以下方式扫码登陆
APP图标
使用APP登录
微信图标
使用微信登录
试题通小程序二维码
联系电话:
400-660-3606
试题通企业微信二维码