Which process converts the sales and operations plan into gross labor hours, floor space, and machine hours?

A
Resource planning
B
Rough cut capacity planning
C
Capacity requirements planning
D
Finite load planning

答案解析

正确答案:A
CPIM PART2-供应链资格认证考试

扫码进入小程序
随时随地练习

相关题目

单选题

The pre-sales and operations planning process meeting should include

单选题

Based on the information provided, the production plan would be
Starting inventory 1500
Forecast 2500
Projected end inventory 1200

单选题

Which of the following information is necessary for determining the production planning horizon?

单选题

A company produces 500 end items for distribution and sales. Which information could be evaluated prior to the end of the month in order to streamline the sales and operations planning process?

单选题

The role of top management in the sales and operations planning process is to

单选题

Critical information required during the operations strategic planning process is

单选题

Which of the following measures best describes performance related to sales and operations planning?

单选题

A MTO company is ready to introduce family that has many of the criteria the market is demanding, which of the follow production strategies is most applicable for the introduction phase of the new product

单选题

Period J F M A M J J A S O N D
Sales plan 50 50 60 60 80 90 70 50 40 40 40 40
Actual sales 51 47 63

Period J F M A M J J A S O N D
Production plan 50 60 60 70 70 70 70 50 50 50 50 40
Actual production 48 60 61

Period J F M A M J J A S O N D
Inventory plan 20 30 30 40 30 10 10 10 20 30 40 40
Actual inventory 20

What's the actual March inventory based on the information provided?

单选题

A company performs sales and operations planning monthly, with a production planning horizon extending four months into the future on a rolling basis. Business planning is performed annually and reviewed monthly. The longest lead time parts are specially items with a lead time of six weeks. The forecasting horizon length should be

关闭登录弹窗
专为自学备考人员打造
勾选图标
自助导入本地题库
勾选图标
多种刷题考试模式
勾选图标
本地离线答题搜题
勾选图标
扫码考试方便快捷
勾选图标
海量试题每日更新
波浪装饰图
欢迎登录试题通
可以使用以下方式扫码登陆
APP图标
使用APP登录
微信图标
使用微信登录
试题通小程序二维码
联系电话:
400-660-3606
试题通企业微信二维码