Which of the following actions would most likely lead to an achievable master production schedule?
答案解析
相关题目
A company intends to cut its backlog from 4 months to 2 months. Annual demand is 360 units. The number of units that should be included in the production plan is
Planning horizon: 18 months
Working days per planning period: 22
Production planning approach: Level
Total demand: 72000units
Beginning inventory: 4800units
Target for ending inventory: 6600
Planned lot size: 2000
The production per planning period required to satisfy this plan in units is closest to
Which of the following results is most likely to occur in a company that does not use a formal sales and operations planning process?
Load smoothing at the production planning level to resolve an overload condition identified by resource planning is an example of
The pre-sales and operations planning process meeting should include
Based on the information provided, the production plan would be
Starting inventory 1500
Forecast 2500
Projected end inventory 1200
Which of the following information is necessary for determining the production planning horizon?
A company produces 500 end items for distribution and sales. Which information could be evaluated prior to the end of the month in order to streamline the sales and operations planning process?
The role of top management in the sales and operations planning process is to
Critical information required during the operations strategic planning process is