For a service level of 98% and a MAD of 52, a lead time of 6 weeks with a forecast of 350 per week, what is the safety stock required?
答案解析
解析:
Forecast Period) =52*1.25*2.05*Square Root of(6) =326.3 and we round up to 327
相关题目
Which of the following product environments is most likely to use actual cost?
An advantage of cycle counting over annual physical inventory is
A company is determing how much floor space to reserve in the layout for the point-of-use storage in order to eliminate centralized storage. The inventory classifications the most useful for initial planning purposes are
Last year a company had an average inventory of $24,000,000 and the cost of sales for they year was $48,000,000, the budget of the year shows the cost of sales increasing by 25% with no increase the average inventory, what inventory turns did the company have, and what will they need to have this year to meet the budget?
In a process industry, which of the following elements decouple the scheduling of sequential stages?
A mix-mas system is a variation of which of the following lot sizing techniques?
A buyer has notified the material planner that a purchase order required in period 2 will not be received until period 3, the first action the planner should take is to
The cost that includes the production cost plus the costs of logistics, such as warehousing, transportation and handling fee is the
Loss caused by scrap, theft, deterioration or evaporation is known as
A process in which a supplier is responsible for maintaining customer inventory level through regularly scheduled reviews of the on-site inventory is