MRP may recalculate planned orders as a direct result of
Which of the following statements about MRP and scheduled receipts is true?
A MTO company has typically used fixed order quantities for its commonly used components. This has resulted in excess inventory over time due to customer changes and new product configurations. The planner should consider which lot sizing techniques to get the problem under control?
Which of the following statements correctly describes allocation logic?
A condition when a normally dependent demand item is not included in a MRP BOM explosion is
A performance measure of MRP is
An action message for a part indicated the part needs to be de-expedited by one week, but the buyer opts to not notify the supplier, the supplier shipped to meet the original requested date and the part has a receipt tolerance of required date minus 2 days and plus 0 days, when the supplier's performance is evaluated, this shipment will show as
A company has a standard product line that is regularly re-engineered to reduce cost and improve quality. When communicating new replenishment requirements to the supplier the buyer must aware of the
A component is defined on only one BOM at level 6, but also has independent demand. Which of the following statements is true?
Period 1 2 3 4 5 6 7 8
Gross requirements 40 10 30 50 50 20 30 40
Scheduled receipts
Projected available 130
order quantity: 40
Safety stock: 10
Lead time: 3 periods
When must a planned order be released to meet a net requirement in period 5?