When using skills and knowledge to coordinate the organizing, planning, scheduling, directing, monitoring, and evaluating of prescribed objective then you are what?
答案解析
解析:
相关题目
A tool that enables a planner to perform bottom-up replanning is
Period 1 2 3 4 5 6 7 8
Gross requirements 40 10 30 50 50 20 30 40
Scheduled receipts
Projected available 130
order quantity: 40
Safety stock: 10
Lead time: 3 periods
What are the net requirements for period 7?
Which of the following types of orders remain unchanged during a MRP run?
Period 1 2 3 4 5 6 7 8
Gross requirements 40 40 50 60 60 80 80 80
Scheduled receipts 100
Projected available 60
order quantity: fixed order qty of 100
Safety stock: 10
Lead time: 2 weeks
The scheduled receipt in the information provided represents a purchase order. MPR would recommend
2 defective inexpensive parts are discovered in a sample during incoming inspection but the lot itself is accepted. The defective parts are
Which of the following statements is true of forecast demand in the MPS as it relates to MRP?
A company has lean relationship with a supplier, a communication technique beneficial for communicating to the supplier for procurement planning over the horizon is a
Which of the following demand fulfillment approaches typically generates the longest delivery time?
The manufacturing environment, where product volume is low and product variety is high for a given item is
Reducing the levels on the BOM reduces
